Utilities have been installing microgrids due to the advancements in the distributed energy resources technologies. Microgrids also improve the resiliency of the system due to their capability to isolate themselves from the grid and run in islanded mode of operation. Microgrid controllers are management systems that can run the microgrids under varied operating condition and enable the smooth operation of microgrids under various system conditions. It is of high value to de-risk the installation of such controllers. Hardware-in-the-loop evaluation is used by controller developers and utilities to evaluate the controllers under stressful conditions to understand the performance and to understand the necessary improvements to the microgrid controller. In this research work, the team has leveraged the existing infrastructure of real-time simulation at the Energy Systems Integration Facility (ESIF) and the capability of the microgrid controller to control assets over the Internet Protocol (IP) to evaluate a university developed microgrid controller in an efficient and cost-effective manner. The full paper will provide the complete setup, the experimental use cases and the results. In this abstract, one use case will be expalined, and the results from the use case is provided.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Prabakar, Kumaraguru, Vallibeygi, Amir, Konakalla, Sai Akhil R., Miller, Brian R, de Callafon, Raymond A., Pratt, Annabelle, Symko-Davies, Martha, Bialek, Thomas. 2020-03-16. Remote Hardware-in-the-Loop Approach for Microgrid Controller Evaluation: Preprint. https://www.osti.gov/biblio/1605699

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Nodal capacity expansion planning with flexible large-scale load siting

We propose explicitly incorporating large-scale load siting into a stochastic nodal power system capacity expansion planning model that concurrently co-optimizes generation, transmission, and storage expansion. The potential operational flexibility of some of these large loads is also taken into account by considering them as consisting of a set of tranches with different reliability requirements, which are modeled as a constraint on expected served energy across operational scenarios. We implement our model as a two-stage stochastic mixed-integer optimization problem with cross-scenario expectation constraints. To overcome the challenge of scalability, we build upon existing work to implement this model on a high performance computing platform and exploit scenario parallelization using an augmented Progressive Hedging Algorithm. The algorithm is implemented using the bounding features of mpisppy, which have shown to provide satisfactory provable optimality gaps despite the absence of theoretical guarantees of convergence. We test our approach and assess the value of this proactive planning framework on total system cost and reliability metrics using realistic testcases geographically assigned to San Diego and South Carolina, with datacenter and direct air capture facilities as large loads.

24 POWER TRANSMISSION AND DISTRIBUTION↗

From zonal to nodal capacity expansion planning: Spatial aggregation impacts on a realistic test-case

Solving power system capacity expansion planning (CEP) problems at realistic spatial resolutions is computationally challenging. Thus, a common practice is to solve CEP over zonal models with low spatial resolution rather than over full-scale nodal power networks. Due to improvements in solving large-scale stochastic mixed integer programs, these computational limitations are becoming less relevant, and the assumption that zonal models are realistic and useful approximations of nodal CEP is worth revisiting. Here, this work is the first to conduct a systematic computational study on the assumption that spatial aggregation can reasonably be used for ISO-scale CEP. By considering a realistic, large-scale test network based on the state of California with over 8000 buses, we find that well-designed small spatial aggregations can yield good approximations but that coarser zonal models may result in large distortions of investment decisions, e.g., capacity under-investment of up to 41% for the lowest resolution model considered.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Multi-facility analysis using metered power data to quantify MRI energy use and utility bill costs across scanner operating modes

This study quantifies the energy consumption of magnetic resonance imaging (MRI) scanners across discrete operating modes during routine clinical workflows, based solely on electrical power measurements. Although previous studies have investigated MRI energy consumption within single hospitals or specific clinical settings, this research provides a broader and more systematic analysis. Researchers analyzed electrical power data and applied a previously developed semi-automatic method for identifying MRI operating modes using load duration curves for 20 MRI scanners across four different U.S. healthcare facilities, encompassing outpatient, inpatient, and mixed-use clinical settings. A key innovation is the inclusion of localized hourly utility rates to estimate costs, a parameter absent in prior literature. Key findings indicate significant variability in energy and cost profiles between weekdays and weekends. Scanner characteristics, including magnet strength, manufacturer, vintage, location, and clinical setting, influenced average daily energy consumption and power thresholds for operating modes. Notably, the clinical setting of a scanner predominantly determines its energy use. For example, the scanners in outpatient facilities consumed more energy. The breakdown of energy usage and costs by operating modes showed scanners spend between 61% and 93% of their time in nonproductive modes, with one outlier spending 34%. Average daily energy use for the scanners in the study ranged from 160 to 1069 kWh, with energy costs ranging from $\$$9 to $\$$149. This study uses an existing framework to quantify MRI energy behavior, leading to insights that can enable improved performance and cost savings across different healthcare environments.

24 POWER TRANSMISSION AND DISTRIBUTION↗