Predicting contamination accumulation in facilities with limited data

Abstract

"In preparation for the James Webb Space Telescope (JWST) launch at Centre Spatial Guyanias (CSG) in French Guiana, particulate contamination accumulation predictions were necessary for each facility in which the hardware would be exposed because the Telescope would be uncovered in each of the facilities and had strict particulate requirements. These included facilities for final integration and testing, fueling, transportation and encapsulation. Minimal heritage data existed from CSG and previous launch campaigns to use as a basis for contamination predictions. Data from the Automatic Transfer Vehicle and Herschel & Planck launch campaigns were used in conjunction with facility monitoring data provided by ESA and data collected during JWST working group visits to CSG. These campaigns were conducted at varying cleanliness levels that were typically less stringent than JWST requirements. Each facility was evaluated using the data provided and likely performance improvement with the addition of High Efficiency Particulate Air filter (HEPA) banks operating when possible. Once the launch campaign was completed, the predicted fallout was compared with actual data collected throughout the campaign. Based on the actual measurements, JWST’s primary and secondary mirrors are likely much cleaner than was expected with the predicted fallout in each facility. "

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Elaine Stewart, Eve Wooldridge, Joe Ward. Predicting contamination accumulation in facilities with limited data. https://ntrs.nasa.gov/citations/20220012513

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Obtaining cryogenic molecular transport data for analysis

The James Webb Space Telescope (JWST) has a primary mirror, made of 18 segments, and a secondary mirror (SM) that are used to direct the light of desired targets. While on orbit, the secondary mirror assembly (SMA) was stowed for approximately 10 days and was subject to molecular contamination outgassing from the cavity of the secondary mirror support structure (SMSS) in-board hinge (IBH) which contains cables, motors, resolvers, and coatings. The main concern during this period before SMA deployment is the accumulation of ice due to the lack of a heater on the SMA. The temperature differentials between the IBH surfaces and SMA could cause redistribution of contaminants. To address this concern, single layer insulation (SLI) was used to create adequate venting and path redirection of outgassing from the IBH. Two separate thermal vacuum tests were performed to quantify this contamination: one Z307 ASTM E 1559 materials test of the radiator paint used on the motor of the IBH and a separate test on a primary mirror backplane assembly (PMBA) qualification engineering test unit (ETU) of the IBH. These tests approximately followed the predicted SMA pre-deployment thermal environment. To quantify source rates in case of a leak, the motor and resolver sides were separated and quartz crystal microbalances (QCM) were used to measure the deposition of water. The SLI redesign and implementation and outgassing measurements to understand leak effects from the IBH were essential to mitigate the deposition of contamination on the SMA.

James Webb Space Telescope, contamination, cleanro↗

Predicting contamination accumulation in facilities with limited data

In preparation for the James Webb Space Telescope (JWST) launch at Centre Spatial Guyanias (CSG) in French Guiana, particulate contamination accumulation predictions were necessary for each facility in which the hardware would be exposed because the Telescope would be uncovered in each of the facilities and had strict particulate requirements. These included facilities for final integration and testing, fueling, transportation and encapsulation. Minimal heritage data existed from CSG and previous launch campaigns to use as a basis for contamination predictions. Data from the Automatic Transfer Vehicle and Herschel & Planck launch campaigns were used in conjunction with facility monitoring data provided by ESA and data collected during JWST working group visits to CSG. These campaigns were conducted at varying cleanliness levels that were typically less stringent than JWST requirements. Each facility was evaluated using the data provided and likely performance improvement with the addition of High Efficiency Particulate Air filter (HEPA) banks operating when possible. Once the launch campaign was completed, the predicted fallout was compared with actual data collected throughout the campaign. Based on the actual measurements, JWST’s primary and secondary mirrors turned out to be much cleaner than what was predicted.

James Webb Space Telescope, contamination, cleanro↗