Utah FORGE Well 78B-32 Daily Drilling Reports and Logs

This data set includes the daily drilling reports and Pason data for well 78B-32 and Schlumberger logs acquired after drilling completion. This well was drilled between June 27th and July 31st of 2021. Also included is raw and processed data for a variety of well data metrics including temperature, porosity, density, and sonic data. This data was taken at the Utah FORGE site as part of the Utah FORGE project.

15 GEOTHERMAL ENERGY↗

Utah FORGE: Well 56-32 Drilling Data and Logs

This dataset consists of drilling data (Pason data spreadsheets, daily reports, days v. depth, mud logs), Schlumberger logs (FMI, shear anisotropy analysis, memory, sonic, array induction/spectral density/dual spaced neutron/gamma ray/caliper, spectral GR/temperature, and Gardner density correlation), and an end of well report (EOWR) for Utah FORGE well 56-32. This is a vertical well that will be used for seismic monitoring. It was drilled between February 7th and February 21st 2021 to a depth of 9,145 feet. More information about this well can be found at: https://utahforge.com/2021/02/09/drilling-progress-of-well-56-32/ (linked below)

15 GEOTHERMAL ENERGY↗

Utah FORGE: Well 16A(78)-32 Drilling Data

This dataset includes survey data, drilling data, daily reports, summaries of daily operations, and rig photos from the drilling of Utah FORGE well 16A(78)-32, which is a highly deviated deep well. It was completed 60 days ahead of schedule. Rig move in began 10/22/2020 and drilling commenced on 10/30/2020, and total depth was reached on 12/18/2020. Drilling was followed by a diagnostic fracture injection test (DFIT), logging, and circulating casing. The rig was released on 1/12/2021. The upper part of the well was drilled vertically through approximately 4,700 feet of sediments before penetrating into high strength, crystalline granite. The well was deviated at a 65 degree angle from vertical after reaching a depth of 6,000 ft. This angle was maintained for the remainder of the well's trajectory. The well ultimately reached a true vertical depth of 8,559 feet, and a total measured depth of 10,987 feet. Preliminary measurements indicate temperatures at the "toe" of the well will exceed 442 degrees F (228 degrees C). Approximately 74 ft of core of the granitic and metamorphic rocks that will form the FORGE reservoir was also recovered.

15 GEOTHERMAL ENERGY↗

Utah FORGE: Well 16B(78)-32 Drilling Data

This drilling data for Utah FORGE well 16B(78)-32 include a well survey, core summary, mud and mud temperature logs, daily reports of the drilling process, and additional data from the Pason oil and gas company. Well 16B(78)-32 serves as the production well for reservoir creation, fluid circulation, and demonstration of heat extraction for the FORGE project. It has been drilled as a doublet approximately 300 feet parallel to and above the injection well 16A(78)-32. The proposed total depth was 10,658 feet, which was exceeded. Spudding began on April 26th, 2023. As of June 20th, 2023, the total depth measured 10,947 feet and the vertical depth measured 8,357 feet. Drilling included the trial use of insulated drill pipe (IDP) from Eavor Technologies, which was considered a success. IDP restricts counter-current heat transfer between drilling fluid inside the drill string and hotter returning fluid in the annulus, thereby ensuring the bottomhole assembly (BHA) remains submerged in cool fluid. Eavor rented 350 joints of IDP to FORGE which were run in two consecutive BHAs at the well. The results of this trial are included here.

15 GEOTHERMAL ENERGY↗

Multi-Sourced Collaboration for the Production and Refining of Rare Elements and Critical Metals (Final Technical Report)

The project objective was to develop a feasible and cost-effective method for recovering rare earth elements (REEs) and critical materials (CMs) from coal and coal byproducts, resulting in high-purity individually separated REEs and CMs. The targeted REEs included Y, Pr, Nd, Gd, Dy, and Sm, with a purity of over 99.5%, while the CMs included Co, Mn, Ga, Sr, Li, Ni, Zn, and Ge, with a purity of over 90%. The project aimed to design a prototype facility capable of producing 1-3 tonnes/day of high-purity REO mixes. The work was divided into four designated circuits: 1) REE extraction and concentration, 2) REE separation and purification, 3) RE metal production, and 4) CM production. To achieve these goals, the project involved 11 tasks, including technology reviews, research, process flow diagram development, mass balance estimation, and preliminary technical-economic analysis. The project team included researchers from the University of Kentucky, University of Alabama and Virginia Tech as well as process specialists from Argonne National Laboratory. MP Materials provided technical support regarding rare earth markets and processing while Alliance Coal performed resource assessment. The project included a market analysis for Nd/Pr, Tb, Dy, Gd, Y, Co, Mn, Li, Sr, Ga, Ni, Zn, and Ge. These analyses provided insights into the supply and demand trends as well as historic and future projections of market price relative to purity requirements for these elements. Two coal resources were selected for the project: the West Kentucky No. 13 (Baker) Seam and an undisclosed lignite resource in the Illinois coal basin. The estimated quantities of REEs in these resources were calculated based on production samples and drilling data. It was estimated that there is adequate supply for an operation producing one metric ton daily of higher purity mixed rare earth oxides (MREO) for approximately 20 years at a site located in western Kentucky. In Circuit 1, project data was obtained from a pilot heap leach and REE concentration facility. It was concluded that the existing circuit, which generated a MREO concentrate, two types of CM mixed products, and Li- and Sr-containing waters, would be suitable feed for circuits 2-4. Data from the first-of-its-kind coal coarse refuse heap leach pilot pad played a crucial role in estimating reliable elemental concentrations of the pregnant leaching solution (PLS). The average total REE concentration in the PLS was found to be 28.6 ppm. In Circuit 2, several concepts were explored including a novel process referred to as solvent-assisted chromatography (SAC). This concept involved a novel columnar reactor that incorporated multiple mixer/settlers, thereby enabling the operation of counter-flowing aqueous and organic phases. Unfortunately, due to project time constraints, a complete fundamental modeling analysis could not be completed to fully evaluate the technology. Molten salt electrowinning was considered as an alternative for circuit 3 following circuit 2 purification circuit utilizing the novel SAC process. A mass and energy balance of Nd reduction to metal in a fluoride containing molten salt electrolyte was conducted. Comparisons were made with the current state of Asian molten salt electrorefining, and potential improvements in siphoning rare earth metals (REM) from the reactor were presented. A cost estimate was performed for the production of 1 tonne per day, which yielded a total of $2.29 million for the nine electrowinning (EW) cells required. The selected option for circuits 2 and 3 was a plasma distillation process, which initially separates rare earth elements (REEs) from other elements. This is followed by selective electrowinning in various ionic liquids. The selection was made on the basis of thermodynamic modeling and experimental data previously published by a project partner. The combination offers an innovative approach to integrated refining and RE metal production. For Circuit 4, an extensive literature review was conducted for the processing of the CMs. The ultimate decision was to utilize a combined plasma and ionic liquid process as well to produce individual high-purity concentrates of Zn, Ni, Co, Mn, and Mg. A separate flowsheet for Li and Sr was recommended, which would yield carbonates of these elements. Due to the lack of suitable experimental data at this time, a process recommendation could not be provided but several methods have been proposed for consideration. Lastly, a techno-economic analysis (TEA) was conducted to assess the effectiveness of the proposed process for further investigation. The TEA results revealed a capital expense (CapEx) of $737 million and an annual operational expense (OpEx) of $220 million. Due to the selected elements, the hypothetical heap leach pad can produce 1 metric tonne per day of REO equivalent, but a conscious decision was made to only treat targeted REEs, resulting in the production of 0.4 metric tonne of REM. An estimated annual revenue of $90.87 million was projected based on standard market pricing information provided by the funding agency. During the TEA, ten different modules were evaluated for costing purposes. The precipitation circuit was identified as the largest single operational expense, followed by the Mg/Mn process due to the amount of treated metal. In terms of capital expenditures, the heap leach process incurred the highest cost, followed by the Mg/Mn process. The scalability of the plasma process is a crucial consideration since the reactors cannot be scaled beyond the largest demonstrated size due to their reliance on surface area of the slag and vapor phase. The purity estimate for the REEs are generally 98%±2% to produce a metal. The purity level being lower than the project objective was due to the lack of specific experimental data needed to tighten the tolerance of the estimates. Based on literature and previous experience, the CMs are estimated as follows; Ga (95%+, metal), Sr (95%+, carbonate), Li (95%+, carbonate), Ni (98%±2%, metal), Zn (95%+, metal sponge), Ge (95%+, metal), Co (98%±2%, metal), and Mn (98%±2%, metal).