Innovative Pathways: Transforming Impact Investments to Working Capital For Early Stage Cleantech Companies: Los Angeles Cleantech Incubator (January 1, 2020 to March 31, 2020)

Project Objectives: The focus for the entirety of the last quarter was on the completion of the pilot loan funding within our portfolio, and the closing out of our DOE-CAP Grant: “Innovative Pathways: Transforming Impact Investments to Working Capital for Early Stage Cleantech Companies.” The fourteenth quarter (Q14) of the program performance was also dedicated toward two main activities: the continued fundraising efforts for a formalized LACI debt fund, as well as finalization of the lending processes for pilot underwriting amongst the LACI Team and with Mission Driven Finance. This quarter marked key successes around the workflows of the DOE-CAP grant, specifically around fund capitalization efforts. Activities during the thirteenth quarter included: 1. Finalization of the DOE-CAP grant activities and work-flows; 2. Due diligence, underwriting and issuance of one (1) loan in Q1 2021 and three (3) in Q4 2020 for technology providers in grant-funded zero emissions mobility & community pilots, in partnership with LACI and local organizations, totaling ten (10) total loans; 3. Development of fundraising and marketing materials, and distribution to 30+ possible funding sources over the course of Q13 & Q14; and 4. Reinvigoration of conversations with Mission Driven Finance, the prospective underwriting partner for key activities and governance documents, and finalization of all loan processing activities once the fund is capitalized

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

User Objectives and Design Approaches for Microgrids: Options for Delivering Reliability and Resilience, Clean Energy, Energy Savings, and Other Priorities

In fall 2019, the National Association of Regulatory Utility Commissioners (NARUC) and the National Association of State Energy Officials (NASEO) initiated a joint Microgrids State Working Group (MSWG), funded by the U.S. Department of Energy (DOE) Office of Electricity (OE). The MSWG aimed to bring together NARUC and NASEO members to explore the capabilities, costs, and benefits of microgrids; discuss barriers to microgrid development; and develop strategies to plan, finance, and deploy microgrids to improve resilience. Based on member input, the MSWG developed two companion briefing papers to answer key questions about microgrids: (1) User Objectives and Design Approaches for Microgrids: Options for Delivering Reliability and Resilience, Clean Energy, Energy Savings, and Other Priorities and (2) Private Sector, State, and Federal Funding and Financing Options to Enable Resilient, Affordable, and Clean Microgrids. Read together, these resources provide readers with an understanding of both why and how customers—whether an investor-owned, cooperative, or municipal utility; federal, state, or local government entity; individual or group of residential, commercial, and/or industrial customers; or other organization—select, design, and pay for microgrid projects.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Cost-Benefit Analysis For Indonesia Building Sector: Whole-Building Cooling Solutions

The Net Zero World (NZW) Initiative Collaborative Work Program with the Government of Indonesia (GoI) includes technical assistance and investment mobilization facilitation to accelerate deployment of energy efficiency technologies and solutions for the building sector. A February 2023 U.S.–Indonesia Joint Workshop on Decarbonizing the Building Sector yielded a NZW Indonesia Building Decarbonization Working Group (NZW IBDWG) with four sub-working groups (SWG): SWG-A National Center, SWG-B Capacity Building, SWG-C Investment and Financing, and SWG-D Pilot Projects. Technical analysis of whole-building cooling solutions for tropical climates of Indonesia was conducted by SWG-A to quantify energy savings, carbon dioxide reductions, and comfort improvements offered by 12 passive or low-energy cooling strategies: ceiling fans with and without thermostat setbacks; cool roofs; cool walls; exterior awnings; exterior shades; interior shades; insulated roofs; insulated walls; low-e windows; solar window films; and natural ventilation. Leveraging the results from SWG-A, cost-benefit analysis (CBA) was conducted by SWG-C to assess the consumer and national costs and impacts associated with these 12 cooling solutions. The evaluation involved estimating life-cycle costs (LCC), payback period (PBP), net present values (NPV), annual electricity burden change for low-income households, and reduced national annual power-sector generation demand by 2030, 2040, 2050, and 2060. This evaluation can help guide Indonesia’s Just Energy Transition Partnership (JETP) investments in policies and programs to advance research, development, deployment, and commercial adoption (RDDCA) of efficient residential building sector cooling technologies and solutions in Indonesia. Four key energy conservation measures (ECM) have been identified to reduce air-conditioning (AC) energy demand in single-family housing in Indonesia: ceiling fan with temperature setback (to 28.1 °Celcius from 25 °C); insulated walls; insulated roof; and cool roof. This study found that low-income households with AC installations in Indonesia currently face a high energy cost burden of approximately 10%. However, by implementing a ceiling fan with temperature setback, this burden could decrease to 2.5% today and further reduce to 1.3% by the year 2060. The PBP for a ceiling fan with temperature setback is one year, indicating one of the lowest LCC and best NPV. In the planned upcoming phase of CBA, a series of building cooling improvement scenarios can be further defined, incorporating more than one ECM in combination with socio-economic factors evaluated in the initial CBA phase. Additionally, the analysis of ECM effects in multifamily housing can be expanded. This broader national analysis aims to encompass a holistic and comprehensive system-level perspective, including factors such as avoided power sector infrastructure investments, domestic job creation, domestic manufacturing job creation, and gross domestic product (GDP) growth.

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

Performance Assurance Planning Guide for Utility Energy Service Contracts: 2025 Edition

Administered by the U.S. Department of Energy's (DOE) Federal Energy Management Program (FEMP), the Utility Program has fostered collaboration among federal agencies and their serving utilities for more than 25 years. The Utility Program supports agencies using Utility Energy Service Contracts (UESCs), a well-developed, effective contracting vehicle that enable the latest approaches to cost-effective energy management at federal sites. Federal agencies have successfully used UESCs to award over 2,000 energy and water efficiency and renewable energy projects, investing approximately $\$$2.8 billion in furthering the Federal Government's efforts to reduce energy intensity. Authorized by 42 U.S. Code section 8256 (10 U.S. Code section 2913 for the Department of Defense), a UESC is a limited-source acquisition between a federal agency and an eligible serving utility for energy management services that generate savings from the implementation of energy- and water -conservation measures (collectively referred to as ECMs), with 42 U.S. Code section 8287 (Defense Federal Acquisition Regulation Supplement, Part 241), providing the term of a UESC, which may extend up to 25 years. Through a UESC, the utility partner assesses designs, and implements the desired ECMs - which can range from lighting retrofits and renewable energy systems, to combined heat and power plants or other technologies and strategies, and may provide financing for the project. The agency may use any combination of appropriations and third-party financing to pay for the project, providing useful flexibility. There is no limit to the project size, big or small, that can be implemented using a UESC. To assist agencies implementing a UESC, FEMP has developed a Utility Energy Service Contract Guide and this companion guidance document to help agencies and their utility partners better understand the best practices for to ensure UESCs continue to perform and generate savings throughout their performance period. These best practices utilize a combination of effective project management, communication, documentation, and a detailed Performance Assurance Plan. This plan is a project specific set of actionable protocols that define important tasks and responsibilities throughout the contract term and reflects the site conditions, complexities, agency capabilities, and operating and maintaining planned ECMs.

29 ENERGY PLANNING, POLICY, AND ECONOMY↗

From Concept to Capital: How Developers Secure Private Investment

With an increased need for funding diversity in hydropower, private capital is becoming more important than ever. Investors are actively seeking opportunities, but what makes a project attractive for investment, and how can companies secure private equity or venture capital backing? This session brings together experts to discuss what capital providers look for in providing financing for hydropower projects. Panelists will explore key barriers - such as the lack of diversified portfolios and long-term revenue certainty - and strategies to overcome them through innovative financing mechanisms, partnerships, and market-driven solutions.

16 TIDAL AND WAVE POWER↗

Operational-based annual energy production uncertainty: are its components actually uncorrelated?

Calculations of annual energy production (AEP) from a wind power plant – whether based on preconstruction or operational data – are critical for wind plant financial transactions. The uncertainty in the AEP calculation is especially important in quantifying risk and is a key factor in determining financing terms. A popular industry practice is to assume that different uncertainty components within an AEP calculation are uncorrelated and can therefore be combined as the sum of their squares. We assess the practical validity of this assumption for operational-based uncertainty by performing operational AEP estimates for more than 470 wind plants in the United States, mostly in simple terrain. We apply a Monte Carlo approach to quantify uncertainty in five categories: revenue meter data, wind speed data, regression relationship between density-corrected wind speed (from reanalysis data) and measured wind power, length of long-term-correction data set, and future interannual variability. We identify correlations between categories by comparing the results across all 470 wind plants. We observe a positive correlation between interannual variability and the linearized long-term correction; a negative correlation between wind resource interannual variability and linear regression; and a positive correlation between reference wind speed uncertainty and linear regression. Then, we contrast total operational AEP uncertainty values calculated by omitting and considering correlations between the uncertainty components. We quantify that ignoring these correlations leads to an underestimation of total AEP uncertainty of, on average, 0.1% and as large as 0.5% for specific sites. Although these are not large increases, these would still impact wind plant financing rates; further, we expect these values to increase for wind plants in complex terrain. Based on these results, we conclude that correlations between the identified uncertainty components should be considered when computing the total AEP uncertainty.

17 WIND ENERGY↗

An overview of wind-energy-production prediction bias, losses, and uncertainties

Abstract. The financing of a wind farm directly relates to the preconstruction energy yield assessments which estimate the annual energy production for the farm. The accuracy and the precision of the preconstruction energy estimates can dictate the profitability of the wind project. Historically, the wind industry tended to overpredict the annual energy production of wind farms. Experts have been dedicated to eliminating such prediction errors in the past decade, and recently the reported average energy prediction bias is declining. Herein, we present a literature review of the energy yield assessment errors across the global wind energy industry. We identify a long-term trend of reduction in the overprediction bias, whereas the uncertainty associated with the prediction error is prominent. We also summarize the recent advancements of the wind resource assessment process that justify the bias reduction, including improvements in modeling and measurement techniques. Additionally, because the energy losses and uncertainties substantially influence the prediction error, we document and examine the estimated and observed loss and uncertainty values from the literature, according to the proposed framework in the International Electrotechnical Commission 61400-15 wind resource assessment standard. From our findings, we highlight opportunities for the industry to move forward, such as the validation and reduction of prediction uncertainty and the prevention of energy losses caused by wake effect and environmental events. Overall, this study provides a summary of how the wind energy industry has been quantifying and reducing prediction errors, energy losses, and production uncertainties. Finally, for this work to be as reproducible as possible, we include all of the data used in the analysis in appendices to the article.

17 WIND ENERGY↗

Technology assessment and citizen action

The importance of citizen participation in the assessment process is discussed, and a system for citizen assessment action is proposed. A national assessment system is outlined. Citizen participation is considered essential in the assessment process, and impediments to effective action taken by citizens are discussed. These impediments are finance, organization and motivation, and information. The establishment of citizens' assessment associations is proposed, whose functioning would be fostered and regulated by the Citizens' Assessment Administration. The organization, functions, and financing of these associations are described. The implications of citizen action are indicated as the extensive use of class action suits, the broad interpretation of associated costs of litigation, and the use of present scientific research as evidence to assert that it is reasonable to conclude that certain consequences are probable to occur in the future.

Mottur, E. R.↗

The Conceptual Design of an Integrated Nuclearhydrogen Production Plant Using the Sulfur Cycle Water Decomposition System

A hydrogen production plant was designed based on a hybrid electrolytic-thermochemical process for decomposing water. The sulfur cycle water decomposition system is driven by a very high temperature nuclear reactor that provides 1,283 K helium working gas. The plant is sized to approximately ten million standard cubic meters per day of electrolytically pure hydrogen and has an overall thermal efficiently of 45.2 percent. The economics of the plant were evaluated using ground rules which include a 1974 cost basis without escalation, financing structure and other economic factors. Taking into account capital, operation, maintenance and nuclear fuel cycle costs, the cost of product hydrogen was calculated at $5.96/std cu m for utility financing. These values are significantly lower than hydrogen costs from conventional water electrolysis plants and competitive with hydrogen from coal gasification plants.

Farbman, G. H.↗

Satellite Power System (SPS) financial/management scenarios

The possible benefits of a Satellite Power System (SPS) program, both domestically and internationally, justify detailed and imaginative investigation of the issues involved in financing and managing such a large-scale program. In this study, ten possible methods of financing a SPS program are identified ranging from pure government agency to private corporations. The following were analyzed and evaluated: (1) capital requirements for SPS; (2) ownership and control; (3) management principles; (4) organizational forms for SPS; (5) criteria for evaluation; (6) detailed description and preliminary evaluation of alternatives; (7) phased approaches; and (8) comparative evaluation. Key issues and observations and recommendations for further study are also presented.

Vajk, J. P.↗

Economics of hydrogen production and liquefaction updated to 1980

Revised costs for generating and liquefying hydrogen in mid-1980 are presented. Plant investments were treated as straight-forward escalations resulting from inflation. Operating costs, however, were derived in terms of the unit cost of coal, fuel gas and electrical energy to permit the determination of the influence of these parameters on the cost of liquid hydrogen. Inflationary influence was recognized by requiring a 15% discounted rate of return on investment for Discounted Cash Flow financing analysis, up from 12% previously. Utility financing was revised to require an 11% interest rate on debt. The scope of operation of the hydrogen plant was revised from previous studies to include only the hydrogen generation and liquefaction facilities. On-site fuel gas and power generation, originally a part of the plant complex, was eliminated. Fuel gas and power are now treated as purchased utilities. Costs for on-site generation of fuel gas however, are included.

Baker, C. R.↗

Market assessment of photovoltaic power systems for agricultural applications in the Philippines

The market potential in the Philippines for stand alone photovoltaic (P/V) systems in agriculture was assessed. Applications include: irrigation, postharvest operation, food and fiber processing and storage, and livestock and fisheries operations. Power and energy use profiles for many applications as well as assessments of business, government and financial climate for P/V sales are described. Many characteristics of the Philippine agriculture and energy sector favorably influence the use of P/V systems. However, serious and significant barriers prevent achieving the technically feasible, cost competitive market for P/V systems in the agricultural sector. The reason for the small market is the limited availability capital for financing P/V systems. It is suggested that innovative financing schemes and promotional campaigns should be devised.

Cabraal, R. A.↗

Market assessment of photovoltaic power systems for agricultural applications in Morocco

Results of a month-long study in Morocco aimed at assessing the market potential for stand-alone photovoltaic systems in agriculture and rural service applications are presented. The following applications, requiring less than 15 kW of power, are described: irrigation, cattle watering, refrigeration, crop processing, potable water and educational TV. Telecommunications and transportation signalling applications, descriptions of power and energy use profiles, assessments of business environment, government and private sector attitudes towards photovoltaics, and financing were also considered. The Moroccan market presents both advantages and disadvantages for American PV manufacturers. The principle advantages of the Moroccan market are: a limited grid, interest in and present use of PV in communications applications, attractive investment incentives, and a stated policy favoring American investment. Disadvantages include: lack of government incentives for PV use, general unfamiliarity with PV technology, high first cost of PV, a well-established market network for diesel generators, and difficulty with financing. The market for PV in Morocco (1981-1986), will be relatively small, about 340 kwp. The market for PV is likely to be more favorable in telecommunications, transport signalling and some rural services. The primary market appears to be in the public (i.e., government) rather than private sector, due to financial constraints and the high price of PV relative to conventional power sector.

Steingass, H.↗

A proposal for risk sharing in the development of a lunar oxygen plant

The production of lunar oxygen for use in a NASA lunar outpost program could provide a profitable investment for nongovernment development, savings for government, and an initiation of a new resource of capital financing for space industrialization. A joint endeavor to share development risks between government and nongovernment investment is proposed, based on some early assessments of technical and financial feasibility for the project. Successful initial negotiations between government and nongovernment investors can establish the requirements for financing the project with private funds.

Duke, Michael B.↗

Fast Quantum Algorithm for Predicting Descriptive Statistics of Stochastic Processes

Stochastic processes are used as a modeling tool in several sub-fields of physics, biology, and finance. Analytic understanding of the long term behavior of such processes is only tractable for very simple types of stochastic processes such as Markovian processes. However, in real world applications more complex stochastic processes often arise. In physics, the complicating factor might be nonlinearities; in biology it might be memory effects; and in finance is might be the non-random intentional behavior of participants in a market. In the absence of analytic insight, one is forced to understand these more complex stochastic processes via numerical simulation techniques. In this paper we present a quantum algorithm for performing such simulations. In particular, we show how a quantum algorithm can predict arbitrary descriptive statistics (moments) of N-step stochastic processes in just O(square root of N) time. That is, the quantum complexity is the square root of the classical complexity for performing such simulations. This is a significant speedup in comparison to the current state of the art.

Williams Colin P.↗

Small Aircraft Transportation System (SATS): A Collaborative Effort Between Nebraska EPSCoR and NASA Langley Research Center

Implementing SATS in Nebraska will require a number of changes, both technical and administrative. SATS will require major improvements in the infrastructure of Nebraska airports. Improving airport infrastructure so that it can accommodate SATS is first and most obvious goal. A second goal is to make airports financially sustainable over the long term with limited federal assistance. A third goal, closely related to the second, is to link the implementation of SATS with anticipated local economic growth. This can leverage local funds without tax increases, enhance the equity of the finance approach, improve planning of facility size, and reduce long-term per unit cost. Many of these goals are national issues, and presumably federal policy will determine how these goals are addressed. This study examines several financing options and discusses their ease of application to Nebraska's airports.

Source record↗

Optimizing Air Transportation Service to Metroplex Airports: Analysis Using the Airline Schedule Optimization Model (ASOM) - Par 2

The air transportation system is a significant driver of the U.S. economy, providing safe, affordable, and rapid transportation. During the past three decades airspace and airport capacity has not grown in step with demand for air transportation; the failure to increase capacity at the same rate as the growth in demand results in unreliable service and systemic delay. This report describes the results of an analysis of airline strategic decision-making that affects geographic access, economic access, and airline finances, extending the analysis of these factors using historic data (from Part 1 of the report). The Airline Schedule Optimization Model (ASOM) was used to evaluate how exogenous factors (passenger demand, airline operating costs, and airport capacity limits) affect geographic access (markets-served, scheduled flights, aircraft size), economic access (airfares), airline finances (profit), and air transportation efficiency (aircraft size). This analysis captures the impact of the implementation of airport capacity limits, as well as the effect of increased hedged fuel prices, which serve as a proxy for increased costs per flight that might occur if auctions or congestion pricing are imposed; also incorporated are demand elasticity curves based on historical data that provide information about how passenger demand is affected by airfare changes.

Donoue, George↗