Evidence of Completion of Milestone 3: Experimental Testbed
Construction and deployment of the experimental testbed encountered scheduling delays, and completion was subsequently further delayed by curtailment of LANL operations due to the COVID-19 pandemic. Between March and October, LANL was in a state of “Limited Operations” such that only certain “mission-critical” work was performed with approximately 25% on-site staffing. In spite of this, much of the lab space preparation was executed and the five initial model house” units were constructed and installed during this period. Still, the pace of construction was impacted by difficulty in coordinating personnel and minimizing contact between workers. Currently, LANL is in the mode of “Normal Operations with Maximum Telework,” which continues to limit the availability of on-site personnel. Nevertheless, Milestone 3 is now complete. This document describes the experiment as it is deployed and provides status for each task for this milestone.