553 records · Page 31

FY 2026 Midyear Report: Seismic Monitoring of Underground Vibration Sources Using Distributed Acoustic Sensing and Seismometers

Safeguards-relevant temporal changes in underground facilities can be observed using geophysical monitoring techniques. Seismic waves, in particular, provide valuable insights into subsurface activities and can serve as an important tool for detecting anomalous events that may indicate containment breaches at geological repositories. This midyear report summarizes ongoing efforts to automatically and rapidly detect and locate anomalous vibration signals that could be indicative of potential containment breaches. Previous work during FY25 focused on compiling continuous seismic datasets from two underground sites and developing a database of continuous waveforms and ground-truth event data derived from multiple sensing modalities. Building on this foundation, we are adapting anomaly detection and geolocation algorithms to explore methods for monitoring underground activities using two relatively low-maintenance sensing technologies: a dense surface geophone array deployed at the Pleasant Gap mine in Pennsylvania, and a three-dimensional fiber-optic cable array for distributed acoustic sensing (DAS) installed in the subsurface at the Sanford Underground Research Facility (SURF) in South Dakota. This report summarizes work conducted during the first two quarters of FY26, during which we refined a dynamic power spectral density (PSD)-based detector, applied it independently to each geophone station, and then combined the per‑station detections with density-based spatial clustering of applications with noise (DBSCAN) to cluster events and produce spatial maps over a nine‑day interval. In addition, we outline plans for a field trial at the Waste Isolation Pilot Plant (WIPP) in New Mexico to compare traditional seismic monitoring approaches with DAS techniques and to evaluate the benefits of combined data analysis. Activities during the past two quarters have included the preparation and submission of a Field Test Plan to WIPP for approval, as well as submission to headquarters for review and feedback.

58 GEOSCIENCES↗

Estimate of Gamma Dose Rates from Arrays of Fermi-1 Blanket Elements During the MEDE Process

The Enrico Fermi Atomic Power Plant Unit 1 (Fermi-1) was a sodium-cooled fast breeder reactor located in Monroe County, Michigan. The reactor was powered by a core of enriched uranium metal alloy driver fuel, which was enveloped by an axial and radial blanket material consisting of depleted uranium metal alloyed with 3 wt.% molybdenum. There are 406 axial and 559 radial irradiated sodium-bonded Fermi-1 blanket assemblies in storage at INL, totaling 34 metric tons of heavy metal. Disposal of the Fermi-1 blanket material directly into a geological repository is prohibited due to the reactive characteristic of its bond sodium. A melt drain evaporate (MEDE) process can effectively remove bond sodium from Fermi-1 blanket material. Consequently, planning is underway to apply a MEDE process to treat the 34 metric tons of heavy metal of irradiated Fermi-1 blanket material. Given the irradiated Fermi-1 blanket material’s relatively low power history and 50+ years of decay, it can be treated in a shielded glovebox. To assess the requisite shielding, the dose rates of the Fermi-1 blanket elements in various process configurations are needed. The method to perform the dose rate calculations is to first generate an average source term and associated photon source spectra for the Fermi-1 blanket material in SCALE and then use the associated photon spectra to calculate dose rates using MCNP6.2 in seven representative geometries. Dose rates in rem/h were calculated on contact (1 cm from outer geometry surface), 30 cm away from outer geometry surface, and 1 m from outer geometry surface at axial heights spanning the length of the blanket material within the geometry. The maximum average dose rate for the single Fermi-1 radial blanket element is ~0.60 rem/h, for the Fermi-1 radial blanket assembly ~1.10 rem/h, for the single Fermi-1 axial blanket element ~0.5 rem/h, for the Fermi-1 axial blanket assembly ~1.01 rem/h, for the MEDE can ~ 0.98 rem/h, for the Fermi Storage Canister ~ 0.83 rem/h, and for the MEDE cans in the DOE Standard Canister ~0.51 rem/h. Based on these maximum average values, the bounding dose rates are assumed to be 3× the average dose rates calculated for the axial blanket material and 7.6× the average dose rates calculated for the radial blanket material, based on the distribution of Fermi-1 blanket material assembly burnup.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Critical Design Elements for an On-Site Mercury Concentration and Holding Facility - 20175

Administrative changes and funding issues have delayed the Department of Energy (DOE) from establishing and commissioning a National Repository for mercury as required under the Mercury Export Ban Act (MEBA) of 2008. In the interim, a few hazardous waste Treatment, Storage, and Disposal Facilities (TSDFs) have been authorized to accept mercury classified as a hazardous waste as under Subtitle C of the Resource Conservation and Recovery Act (RCRA). Waste generators are charged (either by weight or by volume) for the waste they manifest to these TSDFs. In many cases, mercury and mercury compounds have chemically sorbed to (or physically lodged into) the interstitial spaces of a substrate material. This almost always causes the amount of waste generated to be unnecessarily large, due to the extra volume (or weight) of the accompanying, non-mercury materials. Depending on a multitude of factors, it could be financially beneficial for waste generators to take greater control of their mercury affairs by separating these substrate materials from the mercury and mercury compounds that have become associated with them. Building and operating an on-site mercury Concentration and Holding Facility (CHF) could help relieve a waste generator's overall cost burden. The purpose of such CHFs is not to treat or dispose of mercury, but to recover and concentrate mercury from bulky mercury-laden materials to the extent that the host substrate to which the mercury may have previously been sorbed could pass a Toxicity Characteristic Leaching Procedure (TCLP) test and either be disposed of at a conventional landfill, or be disposed of at a hazardous waste landfill, but absent additional restrictions specifically for mercury. A CHF represents a way for waste generators to save money by separating mercury from common host materials, concentrating it, and then safely storing it until transportation to an authorized TSDF takes place This paper focuses on the critical design elements waste generators should consider when designing and operating a mercury CHF. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Evaluation of Techniques for Vegetation Removal from UAV-Based Photogrammetric DSM near WIPP Land Withdrawal Act Boundary, NM

The Waste Isolation Pilot Plant is located within New Mexico's karst landscape and is the United States' only deep geologic radioactive waste repository which isolates transuranic waste from defense activities underground in a bedded salt formation. Characteristic karst topography in this region is made up of material (such as limestone) that can be dissolved by water over a long period of time, and includes features such as springs, surface streams, sinking streams, caves, and sinkholes. Karst features can potentially impact the integrity of the waste repository in the future and compromise WIPP's performance, particularly when coupled with incompatible land-use activities within the Land Withdrawal Act (LWA) boundary as well as increased water withdrawals outside the LWA. In order to better capture the ground surface topography to support hydrology modeling efforts, the U.S. DOE has enlisted FIU to develop a high-resolution digital elevation model (DEM). In a previous field study, a high-resolution digital surface model (DSM) of an adjacent representative site, Basin 6, was developed by photogrammetry using aerial images captured with unmanned aerial vehicles. The DSM generated was based on point clouds representing the entire landscapes, including points of terrain, vegetation and infrastructure. These above-ground features need to be removed to create a DSM/DEM with good representation of the bare ground. In recent years, many techniques including both pre- and post-processing of DSMs, were developed for vegetation removal with varied success. This research focuses on applying and comparing various vegetation removal methods using point clouds generated of the Basin 6 pilot study area. The 3D RGB-based point cloud classification using Python scripts was a modification of the procedure by Themistocleous (2019). The method using Liblas classifies the point cloud three-dimensionally, whereas the method by Themistocleous (2019) is two-dimensional. The preliminary result of the method using Liblas, however, still had a large amount of vegetation remaining compared to the Pix4D Machine Learning method. The vegetation layer remains highly visible in the DEMs processed using the vegetation indices as opposed to the Pix4D Machine Learning method, which produces a DEM where mostly bare ground is seen. Further modifications to the input parameters are required to improve the vegetation vs. bare ground classification using this approach. The next step will be to improve the method using Liblas and to also test other vegetation removal methods found in the literature review to compare them against the two described here.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Development and Advanced Testing of DPC Cement Fillers

The fillers research and development (R&D) program, mostly experimental, is part of a broader R&D program that includes new process modeling and performance assessment of criticality effects and the overall importance of criticality to repository performance (consequence screening). A literature research and consultation effort with experts by Hardin and Brady (2018) identified several potentially effective and workable filler materials including cements (primarily phosphate based), moltenmetal alloys, and low-temperature glasses. Filler attributes were defined, and the preliminary lists were compared qualitatively. Further comparative analysis will be done (e.g., cost estimates) after experimental screening has narrowed the list of alternatives. The research presented here is focused Sandia’s efforts for the development of phosphate-based cement fillers. Molten metal filler research is an ongoing activity at Oak Ridge National Laboratories and is not discussed herein. After the completion of the FY20 research effort the following cement filler compositions were selected for further experimental development work and advanced testing in FY21: 1. Aluminum phosphate cements (APCs); more specifically aluminum oxide / aluminum phosphate (Al 2 O 3 / AlPO 4 ) cements in which Al 2 O 3 serves as the filler material bound by an AlPO 4 binder formed by the reaction of Al 2 O 3 with various phosphate sources; 2. Wollastonite phosphate cements (WPCs), specifically wollastonite and aluminum or calcium aluminum phosphates in which CaSiO 3 serves as the filler material bound by a calcium phosphate that serves as the binder; and 3. Calcium aluminate phosphate cements (CAPCs) specifically grossite (CaAl 4 O 7 ) and hibonite (CaAl 11 O 18 ) fillers bound by an aluminum phosphate that serves as the binder. This effort focused on the optimization and subsequent processing of these three cements to achieve dense and well-consolidated monolithic samples. Upon completion of the FY21 effort the aluminum phosphate cements (APCs) and the calcium aluminate phosphate cements (CAPCs) show the most promise for advanced testing and scale up. We will begin the work in FY22 focused on testing the performance of these two cements in small scale DPCs as well as advanced materials testing to evaluate cement performance under expected radiation doses and representative post-closure geochemical environments.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Grimsel Test Site - A Successful International Underground Research Laboratory for Many Decades - 20429

For more than 35 years, Nagra and its partners from around the world have been conducting underground research projects at the Grimsel Test Site (GTS, www.grimsel.com) to contribute to the development and confirmation of safe geological disposal concepts and for the characterization of suitable host rock formations. Over the years, the results of this internationally recognized research program have been, and continue to be, incorporated directly into exploration programs, modelling, safety, and engineering feasibility studies on options for deep geological repositories. Each project of the GTS program involves field-testing, laboratory studies, design and modelling tasks, and integrates all scientific and technical aspects. Each project phase is planned with a duration of three to five years to facilitate practical and administrative aspects and allow flexibility for updating the overall project plans with the latest findings. Scientific and engineering interaction among the different projects is ensured via an international steering committee meeting. Hosting an IAEA level C radiation- controlled zone, which allows use of radionuclides, including actinides such as thorium, uranium, neptunium, plutonium and americium, in in-situ experiments is one of the reasons why GTS also developed as a center of excellence for work with radioactive tracers under realistic in-situ boundary conditions. Last year, a new five-year program (2019 to 2023) started which includes projects with a planning horizon of decades. The new five-year program includes a new phase of in-situ experiments using radionuclides such as migration experiments in the Colloid Formation and Migration project (CFM), the Long-Term Diffusion experiment (LTD) and the newly established C-14 and I-129 Migration in cement project (CIM). The 'High Temperature effects on Bentonite' (HotBENT) project is starting in the current phase and is studying the effects of elevated temperatures (>175 deg. C) on bentonite materials. As a generic underground research laboratory (URL) it is expected that the GTS will provide in the coming years a platform for international collaboration, knowledge development and knowledge transfer for the next generation of scientists and engineers in the area of radioactive waste disposal and geosciences. A key role regarding knowledge transfer and training is provided by the well-established Grimsel Training Center (GTC), which (beside many URL related issues) also covers many general aspects of radioactive waste management. In this paper we provide an overview of the current program at the GTS, focusing on the experiments that study the migration of radionuclides through engineered barrier materials and the geosphere. (authors)

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Hydrogen Transport in a Model 9979 Shipping Package with Inner Convenience Cans

Radiolytic hydrogen production and accumulation inside containment packages is a concern at any facility responsible for their packaging, storage, transportation, and/or disposal. When hydrogen gas accumulates to concentrations above the Lower Flammability Limit (LFL) which is 4% or 40,000 ppm in air, the possibility of a deflagration or explosion increases. This concern persists over the course of the package lifetime which is unlimited when disposed of by burial or in permanent repositories. Here, we report on a numerical model used to predict the concentration of hydrogen within each layer of a Model 9979 package containing a convenience can assembly. Simulations show the hydrogen concentration to always be highest in the inner convenience can containing the radioactive source. When the radioactive source is within the Los Alamos National Laboratory (LANL) Packaging Limits, the hydrogen concentration is shown to remain well below the LFL at all times including packaging, storage, transportation, and disposal. A hydrogen transport model is presented for a Model 9979 package system containing a nested arrangement of convenience cans, which are tin oxide coated steel cans of various sizes with a slip-lid assembly. The inner convenience can contains the radioactive source material along with an unknown quantity of incidental water acquired from humid air or processing. While visible organic materials such as paper and plastics were purposely excluded from the inner can, it is not possible to claim the wastes are entirely organic free. The inner convenience can is tape sealed and placed into a plastic bag which is horsetail closed (i.e., twisted and taped). The bagged can is placed into an outer convenience can that is also tape sealed. The can assembly is then placed into the 30 gallon drum and subsequently placed inside the 55 gallon drum in the 9979 package. Here we assume hydrogen gas is produced in the inner convenience can from alpha radiolysis of water at a rate dependent on the quantity of uranium isotopes and water present. The hydrogen transport model was used to calculate hydrogen accumulations within the package’s five layers at different times and conditions. These simulations serve two purposes; (i) to build confidence in the model by comparing predicted values to measured values, and (ii) to check the steady state hydrogen concentrations that are approached at long times in the package’s lifetime. Model simulations were compared to gas samples taken from the 30 gallon drum after storage at LANL’s Chemistry and Metallurgy Research (CMR) building for around 500 days. Hydrogen concentration calculations over much longer periods (i.e., more than 270 years) included extreme storage durations, transportation at extreme cold temperatures, and disposal of packages assuming different average temperatures.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

DECOVALEX-2023: Task A Final Report

Task A, also known as HGFrac, examines the fracturing processes that may occur in the Callovo-Oxfordian claystone (COx) in the context of the high-level (HLW) and intermediate-level long-lived (ILW-LL) radioactive waste repository in France. Understanding these processes and improving numerical models to reproduce them will aid in the design, optimization, and safety of the repository. Heat and gas fracturing are studied in two independent subtasks following a stepwise approach: laboratory tests/benchmark exercises, in-situ experiment, and finally, an application case. The in-situ heater experiment aimed to thermally induce a hydraulic fracture; temperature and pore pressure were monitored to detect any evidence of fracturing. The in-situ gas injection experiment aimed to study the effect of the stress orientation and gas injection kinetics on the gas fracturing process. The occurrence of fracturing was monitored by gas pressure measured in the injection interval. In both experiments, the excavation-induced fracture network around the heater/injection boreholes played an important role in the reduction of the compressive stress state, leading to both a tensile and shear failure response of the COx. During the first two years of the project, the research teams working on each task developed and/or proposed numerical approaches for reproducing the occurrence of fracturing in the in-situ experiments. The failure criteria were defined by reproducing the measurements from laboratory extension tests for the heat fracturing subtask. In the gas fracturing subtask, their approaches were used for simulating several benchmark exercises, and an inter-comparison between models was carried out. In both tasks, the developed approaches were compared with a simplified approach considering poro-elasticity for the mechanical behaviour of the COx. Most of the developed approaches are based on a continuous medium that takes into account variations in hydraulic properties due to mechanical degradation, such as plastic deformation or damage. Other approaches implicitly modelled weak planes or embedded discontinuities to reproduce fracture propagation. The potential for fracture initiation was also studied through of a discrete approach. In the second half of the project, the research teams mainly focused on interpretative modelling of two in-situ experiments and a blind prediction exercise to test their respective approaches. The models developed by the research teams were also applied at the repository scale to evaluate fracture initiation in a case study under vi unfavourable conditions, particularly in terms of spacing between High-Level Waste cells. The results showed that the poro-elasticity approach could be an efficient tool for understanding the main processes occurring in the COx. One example is the explicit representation of the excavation-induced fracture network around the boreholes, which yielded acceptable results compared to the measurement data. However, advanced approaches were needed to evaluate the potential increase of the excavation-induced fracture network extend and better understand fracture initiation. The stress analyses carried out by the teams revealed that hydraulic boundary conditions had a strong impact on fracture initiation in the heater experiment. Furthermore, in most cases, the results required higher pore pressure increments to reach fracturing than those measured in the experiment. This implies that the measurements may have been biased by the packer’s capacity to fully isolate the piezometric chambers, leading to lower pressures. On the contrary, there was no agreement on the fracturing mode, as some reported either shear or tensile fracturing, while others reported a combination of the two modes. In the case of gas fracturing, the research teams were limited to the comparison of a single point, which complicated their task. Nonetheless, the numerical results were able to reproduce the measurements and capture processes such as longitudinal gas flow through the excavation-induced fracture network, as suggested by some evidence in the observation piezometric chambers. The numerical models also agreed with the measurements in the sense of higher probability of developing along the injection borehole than radially towards the sound rock. The approaches developed by the research teams showed that they are capable of analysing and reproducing fracture initiation in the COx. However, areas of future work should focus on the fracture propagation and fracture aperture, which were out of the scope of this task. To this end, additional data must be gathered for the parameter characterisation and validation of the numerical models. Nonetheless, various approaches showed promising results as they were able to reproduce fracture development under certain conditions.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

MCNP® Code Version 6.3.2 Theory & User Manual (Rev. 1)

This document acts as a repository of knowledge for the Monte Carlo N-Particle (MCNP) transport computer code. It is maintained alongside the source code and attempts to introduce new users and re-familiarize experienced users with the theory and practices of using the MCNP code for the wide range of particle transport analyses that it is appropriate for. The latest version of the MCNP code, version 6.3.2, provides the Monte Carlo particle transport community with the latest feature developments and bug fixes in the MCNP code. The MCNP code version 6.0 and later is also known as the MCNP6 code.

42 ENGINEERING↗

Preliminary IHLW Formulation Algorithm Description

This report documents the initial algorithm that could be used by the Waste Treatment and Immobilization Plant (WTP) in batching high-level waste (HLW) and glass-forming chemicals (GFCs) in the HLW melter feed preparation vessel (MFPV) (HFP-VSL-00001 and -00005). Not all Hanford tank waste can be accommodated by the models developed for this report and significant expansion of the model boundaries could be achievable to reduce the WTP mission life and total canister production count. The immobilized HLW (IHLW) must meet a series of constraints to be acceptable for disposal in the Monitored Geologic Repository, which are contained in the Specification 1 of the Contract (DOE 2000), the Waste Acceptance Product Specifications (WAPS, DOE 1996), and the Waste Acceptance System Requirements Document (WASRD, DOE 2007). The IHLW Waste Form Compliance Plan (WCP, 24590-HLW-PL-RT-07-0001, Rev 3) specifies that the formulation algorithm will be developed and used to comply with the constraints associated with glass composition and properties. This report is not an engineering calculation, does not provide design input, and is not an engineering study. Algorithm inputs include the chemical analyses of the blended HLW in the HLW blend vessel (HBV) (HLP-VSL-00028, the volume and composition of the MFPV heel, the volume and composition of the MFPV after waste addition, the volume and composition of MFPV batch after GFC addition, the compositions of individual GFCs, and the mass of glass in each canister. In addition to these inputs, uncertainties in the HLW composition and processing parameters are included in the algorithm. Using the above inputs, the algorithm calculates the following outputs: 1) the volume of HLW to be transferred from the HBV to the MFPV, 2) the mass of each GFC for addition to the MFPV, 3) the composition of the glass that will be produced along with uncertainties, and 4) the predicted properties, with associated uncertainties, of the resulting IHLW. The algorithm uses the property-composition models to calculate properties with associated uncertainties and compares them with various constraints to ensure that a processable feed is formulated and a compliant IHLW is produced. The GFC additions are determined using an optimization approach to provide high confidence that the HLW glass will meet all product quality requirements and key processing constraints. For most HLW batches there are many possible glass compositions that meet all constraints. In these cases, the glass composition is optimized for a series of target component concentrations and target property values. The algorithm also incorporates process measurement and product quality uncertainties, based on the work of Piepel et al. (2005). Estimates of the various process and measurement uncertainties that affect glass compositions and predicted glass properties have been previously reported (Piepel et al. 2005, 2006) and the impacts of these estimated uncertainties on the IHLW composition envelope that meets product quality and processing-related properties with sufficient confidence were evaluated. The details of work performed to date to develop this initial GFC addition and batching algorithm are summarized in Sections 4 and 5. An example data set is used to illustrate the calculations of the algorithm summarized in Section 6. Finally, in Section 7, there is a statement of the required work to achieve a final operational IHLW formulation control algorithm. This report is not an engineering calculation, does not provide design input, and is not an engineering study.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

DECOVALEX-2023: Task E Final Report

This is the Task E final report for DECOVALEX-2023. Task E is focused on understanding thermal, two-phase hydrological, and mechanical (TH2M) processes, especially related to predicting brine migration in the excavation damaged zone around a heated excavation in salt. Salt is attractive as a disposal medium for radioactive waste because it is self-healing and is essentially impermeable and essentially non-porous in the far field (away from excavations). Investigation of the short-term (days to years) near-field (centimeters to tens of meters) behavior of salt is important for radioactive waste disposal because this early period strongly controls the amount of brine in a salt repository. Brine leads to corrosion of waste forms and waste packages, and possible dissolution of radionuclides with brine transport being a potential transport vector to the accessible environment. The main test case used in Task E is the ongoing Brine Availability Test in Salt (BATS) heater test located underground at the Waste Isolation Pilot Plant (WIPP) near Carlsbad, New Mexico, USA. The Task was divided into a series of Steps. Step 0 was an introduction to processes in salt, that included matching historical unheated brine inflow data from boreholes at WIPP and matching temperature observations during BATS heater test 1a. Step 1 included validation of models against a thermo-poroelastic analytical solution relevant to heated boreholes in salt, and two-phase flow around an excavation in salt. Step 2 required all the individual components covered in steps 0 and 1 to come together to match observed brine inflow behavior during the BATS 1a heater test. There were a range of approaches from the teams, from mechanistic to prescriptive. Given the uncertainties in the problem, some teams used one- or two-dimensional models of the processes, while other teams included more geometrical complexity in three-dimensional models. The key learning points from Task E have been: • Heat conduction through salt typically requires non-linear thermal conductivity (as a function of temperature), but most models do a good job matching observations, given appropriate adjustments to the applied power and some thermocouple locations. • Thermal pressurization requires coupled thermal-hydrological-mechanical (THM) responses that consider the thermal expansion of the fluid and solid phases. • Initialization of two-phase flow models around a borehole or excavation in salt are more realistically represented as “wetting up”, rather than “drying down” (i.e., the initial state after excavation is mostly dry, rather than mostly wet). • The BATS 1a heater test includes a significant release of brine after the end of heating, which requires a large increase in permeability to recreate. Task E has been a great learning experience for all the teams involved, and feedback from the modeling teams has led to changes in the design of follow-on BATS experiments, which are now ongoing underground at WIPP. There was a balance throughout the task between freedom to model phenomena how each team saw fit, and prescriptiveness in problem design to bring the modeling teams closer together to allow attribution of smaller differences between models to different modeling choices. The modeling approaches seem to go through two phases: an early phase of discovery or testing, and a later phase of refinement and improvement. In future modeling efforts, different field data could be used (e.g., BATS 2) and more time should be included in the processes for teams to make multiple model refinement or even significant changes to their conceptual model or setup, based on lessons learned from the modeling exercise.

12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE W↗

Fiscal Year 2025 Software Quality Assurance Activities for the ARC Software

The continued goal of the ARC SQA project in the Advanced Reactor Technologies program of DOE is to resolve the QA gaps for the ARC software that limit, or prevent, commercialization of the software for industry users. This project started in earnest in fiscal year 2023 which saw the entire code system moved from a SVN repository to a GitLab repository and an associated software quality assurance plan (SQAP) developed and ratified. Most of the QA gaps in the ARC software were identified in collaboration with industry partners and work begin in fiscal year 2023 and continued through 2024 and 2025. The continuous integration testing was extended to RCT, DASSH, and SE2ANL. Minor changes were required to the original continuous integration methodology to make this happen. When full confidence in the methodology is complete, a report will be created to detail the automated regression testing methodology and minor reports will be created to detail the tolerance settings that have been applied to the output for each ARC code. The primary documentation that is missing includes user manuals, user guides, software verification reports, and code coverage assessments. The DASSH, SE2ANL, and SE2RCT manuals were completed this fiscal year. A review of the SE2ANL software identified that it is unrealistic to include updated correlations or different geometry models and it was scheduled for deprecation in favor of DASSH. The SE2ANL manual is essential for SE2RCT as they are similar but quite different in purpose. The only piece of software missing a manual consistent with the source code is NUBOW-3D which is a focus of the coming year. The code coverage report for DIF3D was updated and code coverage reports were created for REBUS, RCT, PERSENT, GAMSRC, and DASSH. Minor coverage issues were identified for all of these pieces of software which did not prevent the work done to transition them to the OneAPI compiler. Because SE2ANL was scheduled for deprecation, it was not transitioned, but it was successfully tested with the OneAPI compiler. This leaves SE2RCT and NUBOW-3D as the only pieces of software not transitioned to OneAPI and further work is required to get SE2RCT to work properly. The SE2RCT software transition will begin early next year while the NUBOW-3D software requires a manual before it can begin. Software verification work has been completed for DIF3D, REBUS, GAMSOR, GAMSRC, VARPOW, EvaluateFlux, and SUMMAR. The PERSENT software verification work was completed this year which was somewhat delayed because of unexpected bugs in the software. The PERSENT manual was updated to detail some of the issues and discuss the bowing reactivity worth feature added in the previous fiscal year. The RCT, DASSH, SE2RCT, and NUBOW-3D software are the only maintained pieces of software without verification reports. The software verification work for DASSH will be a focus in the upcoming fiscal year and it is hoped that some of the test cases created can serve as verification tests for SE2RCT. The NUBOW-3D work will begin when the manual and requirements report are completed. Only minor industry partner software development funds were provided this year. The DASSH software was updated to handle general axial geometry for each assembly and the NUBOW-3D software was updated to incorporate a new input format and better output. Overall progress on resolving the QA gaps has been good this year.

22 GENERAL STUDIES OF NUCLEAR REACTORS↗

DECOVALEX-2023: Task C Final Report

The Full-scale Emplacement (FE) heater experiment at the Mont Terri Underground Rock Laboratory (URL) was designed and conducted by Nagra to replicate an emplacement tunnel of Nagra’s reference repository design at 1:1 scale. Alongside testing the technical feasibility of constructing disposal tunnels, emplacing waste containers in the tunnels and then backfilling them, the main goals of the FE experiment are (1) to obtain a better understanding of the coupled effects of induced thermo-hydro-mechanical (THM) processes that may occur and (2) to validate existing coupled THM models (Müller et al., 2017). A key aspect of ensuring safety for repositories located in low-permeability rock involves minimizing any damage to the rock itself, thereby preserving its integrity and promoting a stable environment Amongst a number of processes that could damage the rock is the increase in pore pressure due to thermal loading caused by heat emitted from the waste. To reduce the potential damage of the rock, it is important to analyse the evolution of heat over time due to the heat load of the containers and assess possible consequences by coupled THM models. The aim of Task C of DECOVALEX-2023 was to build 3D numerical models of the FE experiment, focussing in particular on the heating induced pore pressure change in the Opalinus Clay. Data from a large number of sensors were available from the FE experiment for model comparison. These sensors measured temperature and relative humidity in the bentonite around the heaters, and temperature, pressure and displacement/strain in the surrounding Opalinus clay. Data were available from the start of excavation (April 2012) up to August 2020 for most sensors (more than 5 years from the start of heating in December 2014). To fulfil the overall aim of the task, the work was broken down into a number of steps, starting with simpler models to build confidence in each team’s approach and then moving to more complex models that better represent the FE experiment. Step 0 consisted of 2D benchmark models, gradually increasing the number of processes that are represented from thermal (T) only models in Step 0a, to coupled thermal hydraulic (TH) models in Step 0b with a representation of changing porosity, to coupled thermo-hydro-mechanical (THM) models in Step 0c, where porosity changes are calculated by the mechanical model. A detailed specification of processes, parameters, initial and boundary conditions was provided for this step, with the ambition that all teams would work towards close agreement in their model results, thus building confidence in the model implementations. vi It was not straightforward to achieve agreement between the teams, so additional steps (Step 0b2, 0b3, 0c2, 0c3) were added along with derivation of some analytical solutions against which the models could be compared. The reasons for the differences between teams were investigated and found to be caused primarily by different conceptual model assumptions (including temperature dependence of the thermal expansion of water), different model formulations (including porosity evolution) and differences in modelled domain sizes, boundary conditions and grid discretisation. This demonstrates that comparisons between multiple modelling teams and/or comparison with analytical results and experimental data are highly beneficial in providing an indication of uncertainty in model predictions. At the conclusion of Step 0, almost all teams had achieved a close agreement in model results and those that had not achieved an agreement knew the reason for this. Step 1 moved from 2D models to 3D models of the FE experiment without adding technical features like shotcrete or EDZ, and only considering the heating phase. Initially the 3D model was tightly specified to continue to build confidence in the model implementations (Step 1a). The results of Step 1a were compared to the data from the FE-experiment without the teams seeing the data. The teams were then provided with a sub-set of the data from the FE-experiment and invited to consider how best to use the large dataset for model comparison (Step 1b). Teams were then asked to use the data provided to calibrate their models, only changing material property values rather than adding features or processes to their models (Step 1c). In Step 1, teams were asked to only model the heating phase of the experiment, so pressure in the Opalinus Clay was reported as change in pressure since the initial conditions were specified rather than modelled. The change from 2D to 3D models was accompanied by an increase in the dispersion of results between the teams. Some of this was resolved during the task, but some remained and is potentially due to model discretisation. Calibration of parameters was useful in improving the fit of the models to the data but the remaining differences indicated that the models were missing features or processes. In Step 2, the teams were asked to update their models with additional features and processes as well as calibrating parameters to try and improve the fit of the models to the data. Teams were encouraged to represent ventilation of the open FE tunnel prior to backfilling with heaters and bentonite and in Step 2, the absolute pressure in the Opalinus Clay was compared between the teams. Teams took different approaches, but there was consideration of adding shotcrete and an EDZ into the model, representing stress change during excavation and different approaches to modelling ventilation of the FE tunnel. Overall, the documented results showed a very good agreement for temperature. The results for porewater pressure evolution showed a significant improvement for most teams compared to Step 1c with a good agreement to the measurements for several teams whereas some teams overpredicted the pressure increase and others overpredicted the drainage effect especially for the sensors close to the heater. Step 3 was an opportunity for teams to use the models developed in Step 1 and Step 2 to make predictions about the temperature and pressure changes that will be expected at the FE experiment over the next few years in light of the planned changes in thermal output of the heaters.