Operational and Mission Highlights. A Monthly Summary of Top Achievements, November 2021
A monthly summary of top achievements.
SEARCH · Engineering Papers
Search indexed NASA NTRS and DOE OSTI research on propulsion, heat transfer, battery materials and energy systems. Follow report and document links to the original sources.
Quote a phrase for an exact phrase match. Source license links do not imply unrestricted reuse.
A monthly summary of top achievements.
The Weapons Pit production manufacturing team completed pit build 21-1 assembly operations on December 23, 2020. This build utilized all essential flow sheet steps and included the second -01 long tube cut off extension and welding activity. This is the best build produced in the MC4597-01 pit program to date. Final out-of-line operations, non-destructive evaluation, and radiography was completed during the week of January 4. Depending on the results from high energy radiography, this pit will be considered to be a candidate for CERT-02 and shipment to Lawrence Livermore National Laboratory in support of pit certification. It is notable that this build was completed while concurrently making Plutonium (Pu) metal, producing additional castings, machining Pu parts for Build 22, completing disassembly of two pits, supporting Nightshade B Pu target characterization, and precision machining of Jasper certification base plates.
Abstract not provided.
The Indexing Lab is now complete and includes classified and unclassified computers, safes and work stations. Staff capture metadata and catalog materials, including classified reports, directors’ correspondence and Rocky Flats materials to ensure the holdings are discoverable and retrievable. Access protocols were updated for products related to the LANL Annual Assessment in the Online Vault (OLV) classified repository. The Annual Assessment is a yearly analysis of the weapons systems in the nation’s nuclear stockpile. The Standardization Quality Assessment (SQA) for the Online Vault (OLV) classified repository was completed and contained no findings. Beta testing, or customer validation, began for the metrics database that generates metrics reports and visualizations from NSRC customer projects.
Develop an efficient parallel implementation and assess the performance of local time-stepping (LTS) schemes for the shallow water equations in the Model for Prediction Across Scales (MPAS).
Abstract not provided.
To support the Laboratory’s pit mission, the Associate Laboratory Directorate for Plutonium Infrastructure on January 31, 2022, took the first step in establishing operations at TA-55 that run 24 hours a day, seven days a week.
In early February 2022, Laboratory personnel successfully completed the Qualification Design Review (QDR) for the B61-12 Life Extension Program (LEP). QDR is also known as the Delta FDRAAG, short for Delta Final Design Review and Acceptance Group.
When the Laboratory’s Detonator Production team originally completed manufacturing two ALT939 DEV#1 functional cables — the first development units produced in this lot, team members quickly hit an obstacle when electrical testing for these cables failed. Team members sent the cables out for further testing, which revealed the root cause of failure involved the cables’ connectors. Although a challenging issue to resolve, the team worked together and solved the issue ahead of a stipulated deadline, with the cables completed and shipped to support system tests. The team responsible for this challenging work included members from Detonator Production, Nondestructive Testing & Evaluation, and collaborators from Sandia National Laboratories.
An efficient Picard-based solver is proposed for a novel energy conserving particle integrator preserving all first-order guiding center drifts and correct gyroradius for large time steps in arbitrary (non-uniform) magnetic fields. This research enables the efficient deployment of the novel asymptotic preserving (AP) particle orbit integrator into modern energy-conserving, implicit particle-in-cell codes, delivering a truly multiscale simulation capability.
Abstract not provided.
Abstract not provided.
Abstract not provided.
Researchers can now access newly rediscovered materials related to the hydrogen bomb, including reports, memos, and notes from early contributors such as Edward Teller, Stanislaw Ulam, Richard Garwin, Marshall Holloway, Conrad Longmire and other legendary Los Alamos H-bomb scientists.
Abstract not provided.
Abstract not provided.
Associate Laboratory Director for Plutonium Infrastructure Mark Anthony and a procurement team visited three glovebox fabricators the week of Aug. 23, 2022, to discuss equipment procurement options and assess the vendors’ production capability, factory conditions, and safety records. The team determined that all three fabricators can produce complex gloveboxes and meet Nuclear Quality Assurance-1 standards.