Engineering Papers⌕ Search

SEARCH · Engineering Papers

Results for “alternating current optimal power flow”

Search indexed NASA NTRS and DOE OSTI research on propulsion, heat transfer, battery materials and energy systems. Follow report and document links to the original sources.

Quote a phrase for an exact phrase match. Source license links do not imply unrestricted reuse.

31 records · Page 2

Tightest Mixed-Integer Programming Formulations for Quadratic SCUC Optimization

In this project, we developed new, tighter Mixed-Integer Programming (MIP) formulations for the combined Alternating Current (AC) Security-Constrained Unit Commitment (SCUC) and Security-Constrained Optimal Power Flow (SCOPF). The work addresses a critical challenge in power system operations: efficiently determining which generation units to commit and how to optimally dispatch them while maintaining network reliability constraints for both normal and contingency scenarios. Our efforts: 1. Advance the Understanding of SCUC/SCOPF Modeling: By introducing tighter MIP formulations and leveraging cutting-edge optimization tools (Julia/JuMP, PowerModels.jl), this project has pushed forward the state of the art in efficient power systems scheduling. 2. Enhance Technical and Economic Feasibility: The methods developed provide more accurate and potentially faster solutions to large-scale, realistic scheduling and dispatch problems in electric power systems, which can translate into improved reliability and potentially lower costs for grid operations. 3. Benefit to the Public: Greater efficiency in power system operations leads to cost savings for utilities and end-users. Improved reliability and integration of advanced modeling approaches can facilitate the adoption of clean energy resources and better accommodate uncertainties in renewable generation. Because this technology could impact bulk power markets and reliability, these innovations have far-reaching public benefits in terms of cost savings, reliability, and sustainability.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Bulk Power System Flow Control

On July 28, 2023, the Federal Energy Regulatory Commission (FERC) issued Order Number 2023, targeting an improved generation-interconnection process in the United States. FERC Order No. 2023 requires transmission providers to evaluate transmission technologies, other than network expansion, that could provide system improvements and help expand bulk-power system capacity. Transmission providers must consider technologies that would fall under the category of Grid Enhancing Technologies (GETs), which provide capacity-expansion options other than conventional transmission expansion.

32 - ENERGY CONSERVATION, CONSUMPTION, AND UTILIZA↗

Exploiting Power Flow Manifold to Solve AC Optimal Power Flow

AC optimal power flow has proven difficult to solve with interior point methods on GPUs. This is largely due to challenging linear algebra problems that current state of the art massively parallel linear solvers struggle with. However, the advent of Riemannian optimization techniques and the fact that the power flow equations form a smooth manifold present an alternative approach. In this talk, we present the basics of Riemannian optimization techniques in which optimization is done directly on a manifold. Then we present computational results showing that Riemannian techniques are capable of producing solutions of comparable quality as interior point methods.

AC optimal power flow↗

Recent Developments in Security-Constrained AC Optimal Power Flow: Overview of Challenge 1 in the ARPA-E Grid Optimization Competition

In “Recent Developments in Security-Constrained AC Optimal Power Flow: Overview of Challenge 1 in the ARPA-E Grid Optimization Competition,” we review the state of the art in practical algorithms for scheduling power-systems operations in the short term and the results of the recent competition organized by the U.S. Advanced Research Projects Agency–Energy. We explain the mixed-integer nonlinear formulation used in the competition for nonspecialists in electrical engineering, the context and organization of the competition, and the performance of competitors. We find that the collective approaches and results of competitors provide support for efforts to move nonlinear optimization techniques into industrial applications, as they have proven to be a robust and efficient alternative to current linear approximation techniques.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Decomposable Formulation of Transmission Constraints for Decentralized Power Systems Optimization

One of the most complicating factors in decentralized solution methods for a broad range of power system optimization problems is the modeling of power flow equations. Existing formulations for direct current power flows either have limited scalability or are very dense and unstructured, making them unsuitable for large-scale decentralized studies. Here, in this work, we present a novel sparsified variant of the injection shift factors formulation, which has a decomposable block-diagonal structure and scales well for large systems. We also propose a decentralized solution method, based on the alternating direction multiplier method, that efficiently handles transmission line outages in N-1 security requirements. Benchmarks on multizonal security-constrained unit commitment problems show that the proposed formulation and algorithm can reliably and efficiently solve interconnection-level test systems with up to 6,515 buses with no convergence or numerical issues.

Alternating-method of multipliers (ADMM)↗

Optimal Electric Grid Black Start Restoration Subject to Intentional Threats

Efficient restoration of the electric grid from significant disruptions – both natural and manmade – that lead to the grid entering a failed state is essential to maintaining resilience under a wide range of threats. Restoration follows a set of black start plans, allowing operators to select among these plans to meet the constraints imposed on the system by the disruption. Restoration objectives aim to restore power to a maximum number of customers in the shortest time. Current state-of-the-art for restoration modeling breaks the problem into multiple parts, assuming a known network state and full observability and control by grid operators. These assumptions are not guaranteed under some threats. This paper focuses on a novel integration of modeling and analysis capabilities to aid operators during restoration activities. A power flow-informed restoration framework, comprised of a restoration mixed-integer program informed by power flow models to identify restoration alternatives, interacts with a dynamic representation of the grid through a cognitive model of operator decision-making, to identify and prove an optimal restoration path. Application of this integrated approach is illustrated on exemplar systems. Validation of the restoration is performed for one of these exemplars using commercial solvers, and comparison is made between the steps and time involved in the commercial solver, and that required by the restoration optimization in and of itself, and by the operator model in acting on the restoration optimization output. Publications and proposals developed under this work, along with a path forward for additional expansion of the work, and summary of what was achieved, are also documented.

24 POWER TRANSMISSION AND DISTRIBUTION↗

An Update on the Status of a Reduced Flow Test of a 10MW 700°C sCO2 Integrally Geared Compander

. In order to maintain viability as a future power-generating technology, concentrating solar power (CSP) must reduce its levelized cost of electricity (LCOE). One component of solving this problem is reducing the cost of the power block while simultaneously increasing the efficiency of the thermodynamic cycle. One disruptive technology that has the promise to accomplish this is supercritical CO2 based power cycles. These cycles are conceptually similar to steam cycles; however, they have substantially smaller turbomachinery at equivalent power while also delivering more efficiency at turbine inlet temperatures of 500-700 degrees Celsius. This paper will summarize the current status of a US Department of Energy project to develop machinery to support a 10 MW sCO2 power cycle. The team of Southwest Research Institute® (SwRI®) and Hanwha Power Systems America, proposed to develop an integrally-geared (IG) compressor-expander (compander) for use in a nominal 10 MW-scale concentrated solar power (CSP) supercritical carbon dioxide (sCO2) plant application. This integrally-geared compander (IGC) comprises multiple pinion shafts interconnected on a single bull gear to create a compact package, and utilizes a low-cost, low-speed driver. In addition, the integrally geared architecture allows each pinion to operate at different rotational speeds to optimize performance and easily allow for inter-stage cooling and turbine re-heat to further enhance both stage and cycle efficiency. The close integration of all turbomachinery elements into a single integrally-geared (IG) machine creates a design that lends itself to power block modularization, which makes it suitable for waste heat recovery, fossil fuel power plants, and especially CSP applications. As part of the commercialization of this technology, it is necessary to reduce risk by validation testing of key components. In the current work, the focus is developing a test loop to enable safe testing of the main compressor stage across a wide range of operating conditions, and to validate the mechanical integrity of the turbine at full pressure, temperature, and speed. Developing a test loop for sCO2 requires balancing a number of design alternatives that impact cost, lead time, safety, and performance. The current work discusses the design process for the reduced flow test loop for the compander, and supporting documentation supporting the viability of the test loop

wilkes, jason↗

Titanium-Cerium Electrode-Decoupled Redox Flow Batteries Integrated With Fossil Fuel Assets For Load-Following, Long-Duration Energy Storage

Operation of fossil plants at partial capacity with frequent cycling results in decreased efficiency, increased emissions and increased wear and maintenance. The objective of this project is to advance the integration of a titanium-cerium electrode-decoupled redox flow battery (RFB) system with conventional fossil-fueled power plants through technical and economic system-level studies and component scale-up and R&D. The Ti-Ce chemistry has a pathway to meet the DOE cost targets of $\$$100/kWh and $\$$0.05/kWh-cycle owing to the use of low-cost, earth abundant elemental actives and incorporation of inexpensive carbon felt electrodes and non-fluorinated anion exchange membrane (AEM) separators. The initial unit cell design was scaled up, with some modifications made to improve ease of manufacturing, from 25 cm 2 cell area to 400 cm 2 . Electrochemical tests demonstrated operation at a current density up to 50 mA/cm 2 , which is on par with other commercial RFB offerings. Furthermore, the Ti-Ce technology developed by WashU was evaluated and tested by industrial team partner, Giner, Inc., in their modular 3-cell stack. Several cell design modifications and alternate component material selections were successfully implemented to accommodate this chemistry while reducing polarization and leakage. Results from stack testing show high columbic efficiency and indicate that further optimization of cell compression and components will lead to successful operation of the Ti-Ce ED-RFB over longer duration at the multi-cell stack level. Engineering and cost analysis showed that an RFB system with power output on the order of 100 MW and with a charge/discharge duration of approx. 12 hours is the most cost effective for integration with fossil plants. At this scale, projected cycling of fossil fuel power plants can be significantly reduced. The use of a storage system is shown to reduce the fossil plant standalone cost of electricity by $\$$7/MWh, through increased capacity factor and improved average efficiency, in the scenario of high penetration of renewable power.

20 FOSSIL-FUELED POWER PLANTS↗

Open-source Tools for Solving Grid Optimization Problems: ARPA-e Benchmark Algorithm Overview [Slides]

This document contains the official formulation that will be used for evaluation in Challenge 2 of the Grid Optimization (GO) Competition. Minor changes may occur within the formulation. Entrants will be notified when a new version is released. Changes are not expected to be of a significance that would cause a change in approach for the Entrants. This formulation builds upon the Challenge 1 formulation published in ARPA-E DE-FOA-0001952. Entrants will be judged based on the current official Challenge 2 formulation posted on the GO Competition website (this document, which is subject to change), not the formulation posted in DE-FOA-0001952. Entrants are permitted and encouraged to use any alternative problem formulation and modeling convention within their own software (such as convex relaxation, decoupled power flow formulations, current-voltage formulations, etc.) in an attempt to produce an exact or approximate solution to this particular mathematical program. However, the judging of all submitted approaches must conform to the official formulation presented here.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Voltage Optimization

Voltage optimization refers to a volt-var optimization technique which was originally designed to minimize energy consumption and improve end-use efficiency on the distribution system. This reduces source voltage at a substation, which lowers generation demand, reduces system losses, and improves system stability. This has been the conventional implementation of voltage optimization: focusing on regulation of voltages throughout the distribution system via coordinated adjustments of load tap changers, line-voltage regulators, switched shunt compensation, and the targeted placement of new shunt compensation. These methods have received increased focus following a growth in distributed-energy resources (DERs) interconnecting at the distribution level, given their developing capability to participate in voltage regulation. This is paired with the intermittency challenges they pose, load imbalances, and voltage fluctuations. Voltage optimization has long been an area of extensive research within the distribution system, with various strategies and philosophies demonstrating a range of effects. The conventional focus on the distribution system owes to the typical operation of transmission systems, which assumes firm local resources and flows strictly from generation resources to loads. The strategies employed in distribution have also been optimized for this typically radial configuration and operation of the distribution system.

24 - POWER TRANSMISSION AND DISTRIBUTION↗

Evaluating Variable-Impedance Magnetically-Insulated Transmission Lines as a Risk-Mitigation Measure for Next-Generation Pulsed Power

This project has produced the first detailed characterizations of power flow resulting from applying the “variable-impedance MITL” concept to real-life systems in Sandia’s pulsed power program (Z and next-generation pulsed power (NGPP)). We present simulation results and analyses for constant-impedance versions of both Z and NGPP and survey the operational viability of several variable-impedance re-designs in the parameter space of linear tapers. Circuit modeling (SCREAMER/Bertha) was used to pinpoint promising candidate designs, and EM-PIC (Empire) simulations were used to evaluate these candidates more rigorously. This approach was particularly successful in the Z regime which resulted in the identification of several viable variable-impedance MITL designs for each level. The approach was more challenged in the operating space NGPP occupies, producing data points that speak to a more restrictive design space due to anode plasma turn-on. In the end, we were able to converge on one viable variable-impedance design for the highest inductance line (level “F”) and one for the highest current line (level “A”). Altogether, the body of simulation evidence presented in this report suggest there does exist flexibility in operating space for magnetically-insulated transmission lines (MITLs) having variable geometric impedance to be a potential enabling technology for safely increasing current delivery (and potentially lowering stack voltage) in pulsed-power drivers by manipulating electron losses; however, operating points for a particular design must be carefully screened. Circuit and EM-PIC modeling provided consistent verdicts in safe operating regimes for operational viability, but additional physics such as anode plasma turn-on which is included in Empire but not in SCREAMER/Bertha was found to be a critical factor affecting power flow that lead to different assessments between the codes. It is not always the case that the occurrence of anode plasma caused a design to fail (some designs turned on anode plasma yet still delivered load currents meeting design targets); the details matter such as how early in the pulse anode surfaces break down (and how large a region). However, in every case that it did fail it was found that the feedback from anode plasma was the cause (i.e., turning off the anode plasma model in Empire restored agreement with the circuit model prediction). As circuit simulations represent an efficient and practical means of surveying design space compared to more computationally-expensive approaches such as EM-PIC, it could be prudent to invest in the research and development of models to include the effects of anode plasma such as ion emission in circuit codes. The variable-impedance MITL design is a new concept that enables controlled manipulation of the initial electron losses in the outer MITL and can be tested on Z today. We encourage follow-on work to explore further optimization (including alternative variable-impedance profiles, e.g., having constant dZ/dR), and to confirm the major findings presented in this report by fielding test hardware on actual Z shots.

24 POWER TRANSMISSION AND DISTRIBUTION↗

Quantum/AI Topology-Aware Latency-Adaptive HPC Workflow Scheduling Optimization

The growing demand for more powerful high-performance computing (HPC) systems has led to a steady rise in energy consumption by supercomputing worldwide. This study is focused on comparing our Application-Topology Mapper (ATMapper) to the popular Simple Linux Utility for Resource Management (SLURM) for the purpose of exploring methods that can further optimize job-scheduling within HPC systems. ATMapper is an Artificial-Intelligence based approach to job-scheduling that is currently being enhanced with quantum annealing (QA) to generate optimal schedules faster. We are applying QA to speedup our ATMapper process to achieve higher computing efficiency, thereby reducing HPC energy consumption. Here, we examine how four job-scheduling approaches perform in processor node assignment when using an example network architecture of 4 interconnected nodes. Using a specialized script, we are assessing the schedule of a computation flow with 11 interdependent tasks. The data movements among nodes were tracked to count for the number of interactions (network hops) between nodes needed to complete the tasks. The total number of hops and the job completion time were then used to quantify the efficiency of the different mapping approaches. In addition to SLURM, we also compare our ATMapper to the QA-enabled LBNL TIGER and the D-Wave Distributed Computing processor assignment approaches. The preliminary results showed that our topology-aware, latency-adaptive ATMapper is significantly more efficient when compared to the other scheduling approaches due to its load-imbalance network allocation. The scheduler displayed a computing efficiency of 53% by performing significantly fewer network hops than its alternatives. By reducing the number of hops, ATMapper was able to perform all 11 tasks by using only 3 nodes out of given 4. This research indicates the potential to use QA/AI for HPC job-scheduling. Later, we will test a SLURM simulator program to draw further comparisons on the effectiveness of ATMapper's scheduling approach. The results of this comparison will serve as a baseline for later improving SLURM's performance using a QA-enhanced ATMapper approach.

Caraveo, Braulio [University of Huston - Clear Lak↗

Prototype Modeling for a Light-Trapping Planar-Cavity Enclosed Particle Solar Receiver

Concentrating solar thermal (CST) systems present a promising avenue for affordable and reliable energy production. Solar receivers are key components that determine the efficiency and longevity of these systems. Particle-based solar receivers have emerged as a compelling alternative to traditional technologies, offering several advantages that address limitations in current CST systems. This is especially true as next-generation CST technologies target applications including electricity generation, thermochemical processes, and industrial process heat, many of which necessitate higher operating temperatures than current commercial molten salt systems. Molten-salt thermal energy storage (TES) systems, commonly used in CSP, face challenges related to freezing and corrosion. Particle-based TES systems, in contrast, do not experience these issues, as particles are stable at high temperatures, exceeding 1000 degrees Celsius. This capability allows for a wider range of applications, including those requiring higher temperatures for industrial processes and efficient electricity generation. A novel innovation in particle-based solar receiver technology is the light-trapping planar cavity receiver (LTPCR) configuration developed by NREL. The LTPCR design consists of small cavity-like structures using opaque planar surfaces, enabling efficient capture and absorption of solar energy. A high incident flux concentration at the cavity aperture is absorbed on the receiver walls, and subsequently transferred to particles on the inside of cavities. The particles flow through the system, forming a fluidized bed inside of the receiver panels, effectively capturing the absorbed solar heat. Air is used as a fluidizing medium in this process to enhance particle heat transfer and mixing. The effectiveness of this design lies in its ability to manage solar flux conditions and ensure high solar-to-thermal receiver efficiency. A 100-kW prototype is currently being tested at the King Saud University in Saudi Arabia to assess the receiver performance. A range of modeling analyses for the optical, thermal, and mechanical effects were conducted to assess the performance of the receiver under on-sun conditions. The solar flux resulting from the KSU heliostat field was modeled using NREL SolTrace software and produced up to 600 kW/m2 at the receiver aperture. The solar flux absorbed on the receiver walls was then used within a computational fluid dynamics (CFD) model to predict wall temperature distributions along with radiation and convection loss. A two-phase CFD model was developed for the fluidized bed of silica sand inside the receiver panels to predict local wall-to-particle heat transfer coefficients, particle temperature distributions, and outlet temperature of the particles. We have also conducted analyses to understand the thermomechanical behavior of these innovative enclosed light-trapping solar receivers optimized for particle heating. We used finite element analysis (FEA) to predict the receiver's performance using temperature distributions obtained from CFD and based on the resulting stress profiles, evaluated creep-fatigue damage with a goal of achieving a 30-year service life. Analysis showed a significant impact of the particle-to-wall heat transfer coefficients (HTCs) on receiver performance, with higher HTCs resulting in reduced stress and increased lifespan. For instance, when using Inconel 740H, increasing the HTC from 800 W/m2 K to 1400 W/m2 K increased the creep life from 4,000 hours to over 100,000 hours. This highlights the importance of understanding and optimizing heat transfer in the design of high-efficiency receivers.

14 SOLAR ENERGY↗