Conceptual Design of the Moderator Test Station at the Spallation Neutron Source

We describe the Moderator Test Station (MTS), under construction at the Spallation Neutron Source. We will leverage the Beam Test Facility (BTF) at the Spallation Neutron Source to provide a moderator neutronics test stand with which we will verify the anticipated performance gains expected and required from the innovative moderator concepts central to the SNS Second Target Station (STS) and the future of the First Target Station (FTS). These concepts include large-volume para-hydrogen moderators and high-brightness tube moderators. The MTS will add to the existing BTF a proton beam chopper similar to that already used in the SNS at the RFQ exit (the so-called MEBT chopper), various proton beam transport components, a neutron-producing target, a cryogenic moderator test stand, a reflector-shielding assembly, and a performance assessment neutron beamline. The MTS will provide the ability to test a wide variety of moderators in a prototypic configuration, simultaneously measuring the neutronic performance of the moderator concept central to the anticipated STS gains and developing the instrumentation necessary to provide that performance in a production environment. The presentation will describe the MTS, its progress, and the way we optimize the prototypic nature of the moderators we will test.

Iverson, Erik B↗

Spallation Neutron Source Proton Power Upgrade (PPU) Project: Lessons Learned for CD-4

The SNS PPU project goals were to design, build, install and test the equipment necessary to double the accelerator power from 1.4 MW to 2.8 MW and to deliver a 2.0 MW qualified target. PPU also included the provision of a stub-out in the SNS accumulator-ring-to-target tunnel to facilitate a rapid connection to a new proton beamline for the Second Target Station (STS) project. The power capability was doubled by increasing the proton beam energy by 33% and the peak beam current by 50%, relative to pre-PPU accelerator performance. The project also included modifications to some buildings and services. The PPU project accomplished the energy upgrade by fabricating and installing new superconducting radiofrequency (RF) cryomodules, with supporting RF equipment, in the existing linac tunnel and klystron gallery, respectively. The High Voltage Converter Modulators (HVCM) and klystrons for some of the existing installed RF equipment were upgraded to handle the higher beam current. The increased beam power of 2 MW on the First Target Station (FTS) was enabled by the addition of a new high-volume gas injection system for pressure pulse and cavitation mitigation in the mercury target and a redesigned mercury target vessel.

43 PARTICLE ACCELERATORS↗

Morphology and chemistry of projectile residue in small experimental impact craters

Small-scale impact craters (5-7 mm in diameter) were produced with a light gas gun in high purity Au and Cu targets using soda lime glass (SL) and man-made basalt glass (BG) as projectiles. Maximum impact velocity was 6.4 km/s resulting in peak pressures of approximately 120-150 GPa. Copious amounts of projectile melts are preserved as thin glass liners draping the entire crater cavity; some of this liner may be lost by spallation, however. SEM investigations reveal complex surface textures including multistage flow phenomena and distinct temporal deposition sequences of small droplets. Inasmuch as some of the melts were generated at peak pressures greater than 120 GPa, these glasses represent the most severely shocked silicates recovered from laboratory experiments to date. Major element analyses reveal partial loss of alkalis; Na2O loss of 10-15 percent is observed, while K2O loss may be as high as 30-50 percent. Although the observed volatile loss in these projectile melts is significant, it still remains uncertain whether target melts produced on planetary surfaces are severely fractionated by selective volatilization processes.

Horz, F.↗

On the brittle-ductile behavior of iron meteorites - New experimental constraints

Impact trials were performed at the NASA vertical gun range to study low-temperature brittle-ductile transitions in meteoritic, steel and iron targets. The trials were performed to enhance the data base underlying the concept of formation of planetesimals in collisional coagulation. Impact velocities of 1.6-5.5 km/sec were used, as were temperatures from 100-300 K. Spallation was observed in the tests with meteorite samples, even at room temperature, and brittleness was enhanced at temperature below 200 C. Net mass losses were induced at the higher impact velocities. It is suggested that iron meteorite agglomerations could form in the inner solar region during nebular condensation, but would not form in farther-out regions such as the asteroid belt. The protoplanets could have an iron core, with metallicity decreasing with radius from the core, which may have happened with the earth.

Matsui, T.↗

Modernizing the SNS Control System

The Spallation Neutron Source at Oak Ridge National Laboratory has been operating since 2006. An upgrade to double the machine power from 1.4 MW to 2.8 MW is currently underway and a project to add a second target station is in the preliminary design phase. While each project will add the controls needed for their specific scope, the existing control system hardware, software, and infrastructure require upgrades to maintain high availability and ensure the system will meet facility requirements into the future. While some systems have received new hardware due to obsolescence, much of the system is original apart from some maintenance and technology refresh. Software will also become obsolete and must be upgraded for sustainability. Further, requirements for system capacity can be expected to increase as more subsystems upgrade to smarter devices capable of higher data rates. This paper covers planned improvements to the integrated control system with a focus on reliability, sustainability, and future capability.

White, Karen S.↗

Towards Neutron Transformation Searches

To probe the origins of the baryon asymmetry, baryon number violation, the last unconfirmed Sakharov condition, must be definitively observed experimentally. Similarly, the nature of dark matter is currently unknown, and calls out for new candidates to be investigated. Each of these issues can be considered through the study of neutron transformations.Some rare baryon number violating processes, such as neutron-antineutron transformations, are expected to probe baryogenesis. Here, I show progress on this discovery target through construction of more accurate Monte Carlo models, the design of future detectors, creation of more complete atmospheric neutrino background simulations, and use of automated analysis techniques within the the NNBAR/HIBEAM experimental program at the European Spallation Source (ESS) and the Deep Underground Neutrino Experiment (DUNE). First simulation-based sensitivities for these experiments will be discussed. Modeling of rare neutron-antineutron transformation and subsequent annihilation will be discussed at length for multiple nuclei useful to these and other collaborations. To go along with this work, more comprehensive lepton-scattering nuclear models must be integrated into neutrino event generators for proper atmospheric neutrino background simulations. I discuss the first furnishing of these backgrounds for DUNE, and I highlight a potential path forward for the community in this vein using precisionmore » electron scattering modeling as a facsimile.Aspects of other potentially related neutron – mirror-neutron oscillations pertinent to dark matter and the neutron lifetime anomaly will also be considered for the ESS HIBEAM experiment. Here, I will present the first experimental sensitivity calculations for a broad range of modular experimental setups which will serve as research and design stepping stones toward NNBAR while producing a multitude of physics results over short time scales.« less

72 PHYSICS OF ELEMENTARY PARTICLES AND FIELDS↗

Development of Design for the STS Extraction Magnet System

The Oak Ridge National Laboratory STS Project will enhance the Spallation Neutron Source by adding a new neutron source. The upgrade includes a 30% increase in beam energy and a 50% boost in beam current, doubling the accelerator's power capability to 2.8 MW. The Ring-to-Second-Target Beam Transport (RTST) system is vital in directing high-energy proton beams to the new second target station. New magnets have to fit into a restricted space within the existing beamline to add the new extraction line. New, fast kicker magnets (Pulsed Dipole), a focusing quad with an aperture for both beamlines (Large Quad) and the replacement of existing 21Q40 Quads with 'Narrow Quads' having identical fields as the existing design are Fermilab's responsibility. The design of these magnets poses unique challenges, as in addition to the high requirements on the quality of magnetic fields, they are subject to major restrictions related to their dimensions.

Chernenok, V. [Fermilab] (ORCID:0009000778148215)↗

Slow control and monitoring system at the JSNS 2

The Sterile Neutrino Search at the J-PARC Spallation Neutron Source (JSNS$^2$) experiment aims to search for sterile neutrino oscillations using a neutrino beam from muon decays at rest. The JSNS$^2$ detector contains 17 tons of 0.1$\%$ gadolinium (Gd) loaded liquid scintillator (LS) as a neutrino target. Detector construction was completed in the spring of 2020. A slow control and monitoring system (SCMS) was implemented for reliable control and quick monitoring of the detector operational status and environmental conditions. It issues an alarm if any of the monitored parameters exceed a preset acceptable range. The SCMS monitors the high voltage of the photomultiplier tubes, the LS level in the detector, possible LS overflow and leakage, the temperature and air pressure in the detector, the humidity of the experimental hall, and the LS flow rate during filling and extraction. An initial 10 days of data-taking with a neutrino beam was done following a successful commissioning of the detector and SCMS in 2020 June. In this paper, we present a description of the assembly and installation of the SCMS and its performance.

73 NUCLEAR PHYSICS AND RADIATION PHYSICS↗

Progress towards the completion of the proton power upgrade project

The Proton Power Upgrade project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion in early 2025, 2 MW of beam power will be available for neutron production at the existing first target station (FTS) with the remaining beam power available for the future second target station (STS). The project has installed seven superconducting radio-frequency (RF) cryomodules and supporting RF power systems to increase the beam energy by 30% to 1.3 GeV, and the beam current will be increased by 50%. The injection and extraction region of the accumulator ring are being upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. The first four cryomodules and supporting systems were commissioned in 2022-2023 and supported neutron production at 1.05 GeV, 1.7 MW with high reliability. The first-article 2 MW target was operated successfully for approximately 4400 MW-Hours over two run periods. The long outage began in August 2023 for installation of the remaining technical equipment and construction of the Ring-to-Target Beam Transport tunnel stub that will enable connection to the STS without interrupting operation of the FTS. The upgrade is proceeding on-schedule and on-budget, and resumption of neutron production for the user program is planned for July 2024.

43 PARTICLE ACCELERATORS↗

Progress on the Proton Power Upgrade Project at the Spallation Neutron Source

The Proton Power Upgrade Project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion of the project, 2 MW of beam power will be available for neutron production at the existing first target station with the remaining beam power available for the future second target station. The project will install seven superconducting RF cryomodules and supporting RF power systems and ancillaries to increase the beam energy to 1.3 GeV . The injection and extraction region of the accumulator ring will be upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. Equipment is being received from vendors and partner laboratories, and installation is underway with three major installation outages planned in 2022-2024. The project is planned to be completed in 2025.

43 PARTICLE ACCELERATORS↗

Neutron and antineutron production in accretion onto compact objects

Nuclear reactions in the hot accretion plasma surrounding a collapsed star are a source of neutrons, primarily through spallation and pion-producing reactions, and antineutrons, principally through the reaction p+p yields p+p+n+anti-n. We calculate spectra of neutrons and antineutrons produced by a variety of nonthermal energetic particle distributions in which the target particles are either at rest or in motion. If only neutral particles are free to escape the interaction site, a component of the proton and antiproton fluxes in the cosmic radiation results from the neutrons and antineutrons which leave the accretion plasma and subsequently decay in the interstellar medium. This additional antiproton component could account for the enhanced flux of antiprotons in the cosmic radiation, compared to values expected from the standard leaky-box model of cosmic-ray propagation and confinement. Moreover, the low-energy antiproton flux measured by Buffington et al. (1981) could result from target-particle motion in the accretion plasma. This model for the origin of antiprotons predicts a narrow 2.223 MeV line which could be observable.

Dermer, C. D.↗

Neutron and antineutron production in accretion onto compact objects

Nuclear reactions in the hot accretion plasma surrounding a collapsed star are a source of neutrons, primarily through spallation and pion-producing reactions, and antineutrons, principally through the reaction p+p yields p+p+n+anti-n. We calculate spectra of neutrons and antineutrons produced by a variety of nonthermal energetic particle distributions in which the target particles are either at rest or in motion. If only neutral particles are free to escape the interaction site, a component of the proton and antiproton fluxes in the cosmic radiation results from the neutrons and antineutrons which leave the accretion plasma and subsequently decay in the interstellar medium. This additional antiproton component could account for the enhanced flux of antiprotons in the cosmic radiation, compared to values expected from the standard leaky-box model of cosmic-ray propagation and confinement. Moreover, the low-energy antiproton flux measured by Buffington et al. (1981) could result from target-particle motion in the accretion plasma. This model for the origin of antiprotons predicts a narrow 2.223 MeV line which could be observable.

Dermer, Charles D.↗

Progress on the Proton Power Upgrade Project at the Spallation Neutron Source

The Proton Power Upgrade Project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion of the project, 2 MW of beam power will be available for neutron production at the existing first target station with the remaining beam power available for the future second target station. The project will install seven superconducting RF cryomodules and supporting RF power systems and ancillaries to increase the beam energy to 1.3 GeV . The injection and extraction region of the accumulator ring will be upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. Equipment is being received from vendors and partner laboratories, and installation is underway with three major installation outages planned in 2022-2024. The project is planned to be completed in 2025.

Barbier, Charlotte↗

Progress towards the completion of the proton power upgrade project

The Proton Power Upgrade project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion in early 2025, 2 MW of beam power will be available for neutron production at the existing first target station (FTS) with the remaining beam power available for the future second target station (STS). The project has installed seven superconducting radio-frequency (RF) cryomodules and supporting RF power systems to increase the beam energy by 30% to 1.3 GeV, and the beam current will be increased by 50%. The injection and extraction region of the accumulator ring are being upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. The first four cryomodules and supporting systems were commissioned in 2022-2023 and supported neutron production at 1.05 GeV, 1.7 MW with high reliability. The first-article 2 MW target was operated successfully for approximately 4400 MW-Hours over two run periods. The long outage began in August 2023 for installation of the remaining technical equipment and construction of the Ring-to-Target Beam Transport tunnel stub that will enable connection to the STS without interrupting operation of the FTS. The upgrade is proceeding on-schedule and on-budget, and resumption of neutron production for the user program is planned for July 2024.

Champion, Mark↗

A Compact Gas Liquid Separator for the Spallation Neutron Source Mercury Process Loop

Upgrades at the spallation neutron source (SNS) accelerator at Oak Ridge National Laboratory are underway to double its proton beam power from 1.4 to 2.8 MW. About 2 MW will go to the current first station while the rest will go to the future Second Target Station. The increase of beam power to the first target station is especially challenging for its mercury target. When the short proton beam hits the target, strong pressure waves are generated, causing cavitation erosion and challenging stresses for the target's weld regions. SNS has successfully operated reliably at 1.4 MW by mitigating the pressure wave with the injection of small Helium bubbles into the mercury. To operate reliably at 2 MW, more gas will be injected into mercury to mitigate the pressure wave further. However, the mercury process loop was not originally designed for gas injection, and the accumulation of gas in the pipes is a concern. Due to space constraints, a custom gas liquid separator (GLS) was designed to fit a 90-deg horizontal elbow space in the SNS mercury loop. Simulations and experiments were performed, and a successful design was developed that has the desired efficiency while keeping the pressure losses acceptable.

42 ENGINEERING↗

Comparison of the Neutronic Performance of IRP-1 and IRP-2 at SNS

The Spallation Neutron Source (SNS) operated from start-up, in May 2006, through December, 2017 before replacing the Inner Reflector Plug (IRP). This component is the most costly and time-consuming “regular maintenance” replacement foreseen in the operation of the First Target Station (FTS). The IRP includes beryllium reflector blocks, steel and aluminum support structures, aluminum moderator vessels (which in turn include gadolinium and cadmium neutron poisons) and water coolant systems. The lifetime of this multi-million dollar component is driven by poison and decoupler burnup in moderator vessels. The moderators include these neutron poisons to best match neutron beam performance with scattering instrument needs. The burnup that comes with use changes the performance of the moderators until they no longer server their intended purpose. The reasonable desire to maximize the IRP lifetime means that the moderator performance at the Beginning Of Life (BOL) is significantly “over poisoned” and different from the performance at moderator End Of Life (EOL). Upon installation of the second IRP article, IRP-2, the SNS Neutronics team characterized the performance of the neutron beamlines in order to assess the differences between them, primarily by comparing the EOL performance of IRP-1 to the BOL performance of IRP-2. While IRP-2 was largely similar to IRP-1 in its conceptual design, there were some differences in the specific design of IRP-2 to support enhanced manufacturability, and the change from IPR-1 to IRP-2 coincided with the replacement of the light water in the IRP cooling loop with heavy water, as had been intended in the SNS design but not implemented during construction because of heavy water availability.

21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS↗

Measurements of 15.11-MeV gamma-ray flux produced in the reactions C-12(p, p')-C-12*(15.11 MeV) and O-16(p, p' alpha)-C-12*(15.11 MeV)

The flux of 15.11 MeV gamma rays relative to the flux of 4.44 MeV gamma rays which are emitted from the corresponding states of C-12 are a sensitive measure of the spectrum of exciting particles in solar flares and other cosmic sources. Emission of 15.11 MeV gamma rays may result not only from the direct excitation of C-12 but also from the interaction O-16 (p,p' alpha) C-12* sup 15.11 MeV. Although the cross sections for the direct reaction was studied extensively, the cross section for the spallation interaction with O-16 is not reported in the literature. Preliminary measurements demonstrated the feasibility of measuring the production of 15.11 MeV gamma rays by proton interactions with O-16 using the University of Maryland cyclotron facility. For both carbon and oxygen targets the flux of 15.11 MeV gamma rays is being measured relative to the flux of 4.44 MeV gamma rays. The gamma ray emission from de-excitation of the giant dipole resonances is being measured.

Lapides, J. R.↗

Control System Plans for SNS Upgrade Projects

The Spallation Neutron Source at Oak Ridge National Laboratory is planning two major upgrades to the facility. The Proton Power Upgrade project, currently underway, will double the machine power from 1.4 to 2.8 MW by adding seven additional cryomodules and associated equipment. The Second Target Station project, currently in conceptual design, will construct a new target station effectively doubling the potential scientific output of the facility. This paper discusses the control system upgrades required to integrate these projects into the existing EPICS based control systems used for the machine and neutron instrument beamlines. While much of the control system can be replicated from existing solutions, some systems require new hardware and software. Operating two target stations simultaneously will require a new run permit system to safely manage beam delivery.

Hartman, Steven↗