Engineering PapersSearch

DOE OSTI · 2571995

Powernet in Farms Project

Abstract

Coordinating behind-the-meter (BTM) distributed energy resources (DERs) is critical to ensuring efficiency and reliability for consumers facing an increasingly variable grid supply. Outside of very controlled environments, however, such coordination of heterogeneous resources at scale has remained a challenge due to harsh field conditions, the lack of adequate communication infrastructure, and the difficulty of modeling the system. The intent of this research was to refine the Powernet system deployed in a California dairy farm to achieve the following objectives: a) validate the results of the previous deployment and b) validate new hypothesis about system performance based on the simulation of the new system. The new system design would reduce the overall system cost, and achieve a payback period of less than 3 years, demonstrating the feasibility of such system and its relevance for a segment not well known for technology advancements in power systems. The new proposed system was significantly cheaper than the original design, which would enable the solution to be cost effective and likely economically viable. However, due to significant delays in project start date which affected funding availability, overlap with prior scheduled mandatory military leave from key members of the project team, and customer drop-out, due to the significant delays, which could not be replaced in time, caused the project to be ended prior to completion.

Explore related subjects

Keep this discovery

Explore connections, maps & timelines

BibTeXRIS

Rajagopal, Ram [Stanford Univ., CA (United States)]. 2025-02-21. Powernet in Farms Project. https://doi.org/10.2172/2571995

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related reports

Nodal capacity expansion planning with flexible large-scale load siting

We propose explicitly incorporating large-scale load siting into a stochastic nodal power system capacity expansion planning model that concurrently co-optimizes generation, transmission, and storage expansion. The potential operational flexibility of some of these large loads is also taken into account by considering them as consisting of a set of tranches with different reliability requirements, which are modeled as a constraint on expected served energy across operational scenarios. We implement our model as a two-stage stochastic mixed-integer optimization problem with cross-scenario expectation constraints. To overcome the challenge of scalability, we build upon existing work to implement this model on a high performance computing platform and exploit scenario parallelization using an augmented Progressive Hedging Algorithm. The algorithm is implemented using the bounding features of mpisppy, which have shown to provide satisfactory provable optimality gaps despite the absence of theoretical guarantees of convergence. We test our approach and assess the value of this proactive planning framework on total system cost and reliability metrics using realistic testcases geographically assigned to San Diego and South Carolina, with datacenter and direct air capture facilities as large loads.

24 POWER TRANSMISSION AND DISTRIBUTION

From zonal to nodal capacity expansion planning: Spatial aggregation impacts on a realistic test-case

Solving power system capacity expansion planning (CEP) problems at realistic spatial resolutions is computationally challenging. Thus, a common practice is to solve CEP over zonal models with low spatial resolution rather than over full-scale nodal power networks. Due to improvements in solving large-scale stochastic mixed integer programs, these computational limitations are becoming less relevant, and the assumption that zonal models are realistic and useful approximations of nodal CEP is worth revisiting. Here, this work is the first to conduct a systematic computational study on the assumption that spatial aggregation can reasonably be used for ISO-scale CEP. By considering a realistic, large-scale test network based on the state of California with over 8000 buses, we find that well-designed small spatial aggregations can yield good approximations but that coarser zonal models may result in large distortions of investment decisions, e.g., capacity under-investment of up to 41% for the lowest resolution model considered.

24 POWER TRANSMISSION AND DISTRIBUTION

Multi-facility analysis using metered power data to quantify MRI energy use and utility bill costs across scanner operating modes

This study quantifies the energy consumption of magnetic resonance imaging (MRI) scanners across discrete operating modes during routine clinical workflows, based solely on electrical power measurements. Although previous studies have investigated MRI energy consumption within single hospitals or specific clinical settings, this research provides a broader and more systematic analysis. Researchers analyzed electrical power data and applied a previously developed semi-automatic method for identifying MRI operating modes using load duration curves for 20 MRI scanners across four different U.S. healthcare facilities, encompassing outpatient, inpatient, and mixed-use clinical settings. A key innovation is the inclusion of localized hourly utility rates to estimate costs, a parameter absent in prior literature. Key findings indicate significant variability in energy and cost profiles between weekdays and weekends. Scanner characteristics, including magnet strength, manufacturer, vintage, location, and clinical setting, influenced average daily energy consumption and power thresholds for operating modes. Notably, the clinical setting of a scanner predominantly determines its energy use. For example, the scanners in outpatient facilities consumed more energy. The breakdown of energy usage and costs by operating modes showed scanners spend between 61% and 93% of their time in nonproductive modes, with one outlier spending 34%. Average daily energy use for the scanners in the study ranged from 160 to 1069 kWh, with energy costs ranging from $\$$9 to $\$$149. This study uses an existing framework to quantify MRI energy behavior, leading to insights that can enable improved performance and cost savings across different healthcare environments.

24 POWER TRANSMISSION AND DISTRIBUTION