Abstract
In support of the ongoing environmental protection mission at the Hanford Site, led by Washington River Protection Solutions (WRPS), the cold spray team has continued development of the tank refurbishment technology. Orano Federal Services, along with subcontractors VRC Metal Systems (VRC) and Robotic Technologies of Tennessee (RTT), have worked with WRPS experts to refine the tools demonstrated in Phase 1 of this project, with the potential to refurbish double shell tanks (DST)s on the Hanford Site, extending the service lives of these vital waste storage facilities.