External tank processing from barge to pad

Abstract

Delivery and launch readiness events for the External Tanks (ET) are discussed. The ET is off-loaded at the KSC Barge Turning Basin and towed to the Vertical Assembly Building (VAB), High Bay Transfer Aisle. It is erected vertically and placed in the ET Checkout Area of High Bay 2 or 4 for standalone checkout. At the completion of checkout the ET is transferred to storage or to the Integration Area of High Bay 1 or 3 for SRB and Orbiter Mate. A Systems Integration Test performed with the Orbiter and Solid Rocket Booster is described. Final checkout activities are also described.