Abstract
The proper program execution of the switch selector commands that provide sequencing signals to the launch vehicle hardware was verified. Correct execution of each step necessary to activate a switch selector command and maintenance of the minimum timing requirements between steps are verified through analysis of a series of 6D/LVDC intermediate timing cases. Nominal and perturbed switch selector feedback conditions are simulated to verify correct processing of all realistic and timing combinations. A command which is in progress can be properly terminated by issuance of a forced reset. This is verified by forcing the conditions which require a forced reset and observing that the proper termination is completed.