Engineering Papers⌕ Search

Engineering topics

White, Karen S.

Publications and source records attributed to White, Karen S..

Progress towards the completion of the proton power upgrade project

The Proton Power Upgrade project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion in early 2025, 2 MW of beam power will be available for neutron production at the existing first target station (FTS) with the remaining beam power available for the future second target station (STS). The project has installed seven superconducting radio-frequency (RF) cryomodules and supporting RF power systems to increase the beam energy by 30% to 1.3 GeV, and the beam current will be increased by 50%. The injection and extraction region of the accumulator ring are being upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. The first four cryomodules and supporting systems were commissioned in 2022-2023 and supported neutron production at 1.05 GeV, 1.7 MW with high reliability. The first-article 2 MW target was operated successfully for approximately 4400 MW-Hours over two run periods. The long outage began in August 2023 for installation of the remaining technical equipment and construction of the Ring-to-Target Beam Transport tunnel stub that will enable connection to the STS without interrupting operation of the FTS. The upgrade is proceeding on-schedule and on-budget, and resumption of neutron production for the user program is planned for July 2024.

Champion, Mark↗

Progress on the Proton Power Upgrade Project at the Spallation Neutron Source

The Proton Power Upgrade Project at the Spallation Neutron Source at Oak Ridge National Laboratory will increase the proton beam power capability from 1.4 to 2.8 MW. Upon completion of the project, 2 MW of beam power will be available for neutron production at the existing first target station with the remaining beam power available for the future second target station. The project will install seven superconducting RF cryomodules and supporting RF power systems and ancillaries to increase the beam energy to 1.3 GeV . The injection and extraction region of the accumulator ring will be upgraded, and a new 2 MW mercury target has been developed along with supporting equipment for high-flow gas injection to mitigate cavitation and fatigue stress. Equipment is being received from vendors and partner laboratories, and installation is underway with three major installation outages planned in 2022-2024. The project is planned to be completed in 2025.

Barbier, Charlotte↗

Modernizing the SNS Control System

The Spallation Neutron Source at Oak Ridge National Laboratory has been operating since 2006. An upgrade to double the machine power from 1.4 MW to 2.8 MW is currently underway and a project to add a second target station is in the preliminary design phase. While each project will add the controls needed for their specific scope, the existing control system hardware, software, and infrastructure require upgrades to maintain high availability and ensure the system will meet facility requirements into the future. While some systems have received new hardware due to obsolescence, much of the system is original apart from some maintenance and technology refresh. Software will also become obsolete and must be upgraded for sustainability. Further, requirements for system capacity can be expected to increase as more subsystems upgrade to smarter devices capable of higher data rates. This paper covers planned improvements to the integrated control system with a focus on reliability, sustainability, and future capability.

White, Karen S.↗

Progress on the Proton Power Upgrade at the Spallation Neutron Source

The Proton Power Upgrade Project at the Spallation Neutron Source (SNS) at Oak Ridge National Laboratory will double the proton power capability from 1.4 to 2.8 MW. This will be accomplished through an energy increase from 1.0 to 1.3 GeV and a beam current increase from 26 to 38 mA. The energy increase will be accomplished through the addition of 7 cryomodules to the linear accelerator (Linac). The beam current increase will be supported by upgrading several radio-frequency systems in the normal-conducting section of the Linac. Upgrades to the accumulator ring injection and extraction regions will accommodate the increase in beam energy. A new 2-MW-capable target and supporting systems will be developed and installed. Conventional facility upgrades include build-out of the existing klystron gallery and construction of a tunnel stub to facilitate future beam transport to the second target station. The project received approval to proceed with construction in October 2020. Procurements are in progress, and some installation activities have already occurred. Most of the installation will take place during three outages in 2022-2023. The project early finish is planned for 2025.

Barbier, Charlotte↗

Control System Plans for SNS Upgrade Projects

The Spallation Neutron Source at Oak Ridge National Laboratory is planning two major upgrades to the facility. The Proton Power Upgrade project, currently underway, will double the machine power from 1.4 to 2.8 MW by adding seven additional cryomodules and associated equipment. The Second Target Station project, currently in conceptual design, will construct a new target station effectively doubling the potential scientific output of the facility. This paper discusses the control system upgrades required to integrate these projects into the existing EPICS based control systems used for the machine and neutron instrument beamlines. While much of the control system can be replicated from existing solutions, some systems require new hardware and software. Operating two target stations simultaneously will require a new run permit system to safely manage beam delivery.

Hartman, Steven↗

Moving Beyond Bias

The benefits of diverse work groups have been well documented, and our leaders speak of the need for our laboratories to become more diverse and inclusive. Despite these motivators, the field of accelerator controls remains strikingly homogeneous. This trend continues despite many long standing programs to attract underrepresented groups to STEM careers and the explicit desire of leadership to create more inclusive organizations. Research consistently points to the strong role implicit bias plays in preventing organizations from truly providing equal opportunities. The desire to become more diverse must be coupled with a strong culture, cultivated to change deeply rooted practices which influence recruiting, hiring, development, and promotion decisions based on stereotypes rather than accomplishments and abilities. Real change in this arena requires intentional action across the board, not just from human resources and underrepresented groups. This paper discusses practical approaches to changing organizational culture to enable diverse work groups to grow and thrive.

White, Karen S.↗

Speaking of Diversity

Historically, attendance at the International Conference on Accelerator and Large Experimental Physics Control Systems has not been particularly diverse in terms of gender or race. In fact, the lack of diversity amongst the attendees was noted during the closing session of the 2015 conference by an invited speaker from outside the accelerator community. Informal discussion and observations support the assertion that our conference attendance reflects the diversity of the broader accelerator controls workforce. Facing very low participation of women in our field and even lower minority representation, it is important to examine this issue as studies point to the importance of diverse work groups to spark innovation and creativity as catalysts to solving difficult problems. This paper will discuss diversity and inclusion in the disciplines that comprise the accelerator controls workforce, including background, barriers and strategies for improvement.

White, Karen S.↗

Technical Design Report, Second Target Station

The Second Target Station (STS) is a proposed upgrade for SNS. It includes a doubling of the accelerator power and an additional instrument hall. The new instrument hall will receive a 467 kW 10 Hz beam. The parameters and preliminary design aspects of the STS are presented for the accelerator, target systems, instrument hall, instruments and civil construction aspects.

43 PARTICLE ACCELERATORS↗