The feasibility of less spacious, less costly underground rail mass transit system designs is studied. The major cost saving expected from alternative tunnel designs results from using precast concrete segment liners in place of steel. The saying expected for a two-foot decrease in the diameter of twin, single track tunnels is about two million dollars per route mile from 13 million dollars for precast concrete segment liners (a saving of about 16%). The cost per route-mile of a double track tunnel appears to be 15 to 25% higher than for the twin, single track tunnels. The effective cost saving expected from stations with four-car train capability instead of the usual eight-car trains is nearly 25% or seven million dollars per route mile. The saving in station costs can be obtained while improving service to the user (lower transit time and less waiting for trains) up to a capacity of 36,000 riders per hour in each direction.